Canada Offshore Renewable Energy Regulations: SOR/2024-272
Canada Gazette, Part II, Volume 159, Number 1
Registration
SOR/2024-272 December 16, 2024
CANADIAN ENERGY REGULATOR ACT
P.C. 2024-1328 December 16, 2024
Her Excellency the Governor General in Council, on the recommendation of the Minister of Natural Resources, makes the annexed Canada Offshore Renewable Energy Regulations under section 312 of the Canadian Energy Regulator Act footnote a.
TABLE OF PROVISIONS
Canada Offshore Renewable Energy Regulations
Interpretation
- 1 Definitions
- 2 Incorporation by reference
General Requirements
- 3 Carrying on work or activities
- 4 Level of detail
PART 1
Offshore Renewable Energy — Wind Energy
Application
5 Application
Application for Authorization and Conditions of Authorization
Requirements for All Applications
6 Contents
Conditions of Every Authorization
- 7 System and plans
- 8 Management system
- 9 Safety plan
- 10 Environmental protection plan
- 11 Emergency management plan
Site Assessment
12 Application — additional contents
Construction, Operation and Maintenance
- 13 Application — additional contents
- 14 Additional conditions — construction
- 15 Facility design report
- 16 Fabrication and construction report
- 17 Facilities reliability report
- 18 Additional conditions — operation and maintenance
- 19 Integrity management program
Decommissioning and Abandonment
- 20 Application — additional contents
- 21 Additional conditions — decommissioning and abandonment
- 22 Decommissioning and abandonment plan
General Requirements for Operators
Management System and Associated Plans
- 23 Implementation
- 24 Financial and human resources
Integrity Management Program and Quality Assurance Program
- 25 Integrity management program
- 26 Quality assurance program
Other Requirements
- 27 Carrying on of authorized work or activities
- 28 Navigational safety zones
- 29 Design requirements
- 30 Target levels
- 31 Critical software
- 32 Software-dependent control systems
- 33 Rescue boat
- 34 Requirements for vessels
- 35 Evacuation systems and equipment
- 36 Third-party assessment
- 37 Landing area
- 38 Procedures and training program
- 39 Access to documents and information
Certifying Authority and Certificate of Fitness
- 40 Certifying authority
- 41 Operator’s obligations
- 42 Scope of work
- 43 Performance of functions
- 44 Certificate of fitness
- 45 Inspection plans
- 46 Independence and impartiality
- 47 Change of certifying authority
- 48 Annual report
PART 2
Offshore Renewable Energy — Other Than Wind Energy
Application
49 Application
Requirements for All Applications
50 Contents
Conditions of Every Authorization
- 51 Plans
- 52 Safety plan
- 53 Environmental protection plan
- 54 Emergency management plan
Implementation of Plans and Other Requirements
- 55 Implementation
- 56 Conduct of authorized work or activities
- 57 Navigational safety zones
- 58 Design requirements
- 59 Rescue boat
- 60 Requirements for vessels
- 61 Evacuation systems and equipment
- 62 Access to documents and information
PART 3
Notification, Investigation, Reporting and Record-Keeping Requirements for Operators
- 63 Application
- 64 Notification of incidents
- 65 Periodic reports
- 66 Final report
- 67 Record keeping
PART 4
Coming into Force
68 Registration
Canada Offshore Renewable Energy Regulations
Interpretation
Definitions
1 The following definitions apply in these Regulations.
- Act
- means the Canadian Energy Regulator Act. (Loi)
- certifying authority
- means an organization approved by the Regulator under subsection 40(2). (autorité de certification)
- control system
- means any system, station or panel used to control the operation and monitor the status of the equipment used for an offshore renewable energy project or offshore power line. (système de contrôle)
- operations site
- means a site where authorized work or activities are carried on in relation to an offshore renewable energy project or offshore power line. (emplacement des opérations)
- operator
- means an applicant for or holder of an authorization referred to in section 298 of the Act. (exploitant)
- physical and environmental conditions
- means any physical, geotechnical, seismic, oceanographic, meteorological or ice conditions that might affect authorized work or activities. (conditions physiques et environnementales)
- reportable incident
- means any of the following incidents that occur in relation to an offshore renewable energy project or offshore power line:
- (a) a loss of life;
- (b) an injury that prevents an employee from reporting for work or from effectively performing all the duties connected with the employee’s regular work on any day subsequent to the day on which the injury occurred, whether or not that subsequent day is a working day for that employee;
- (c) a fire or explosion;
- (d) a collision;
- (e) any incident that has an adverse effect on the environment, produces debris or introduces into the environment any substance or form of energy that is likely to have an adverse effect on the environment, unless that adverse effect, production or introduction is authorized or explicitly anticipated in an application for an authorization;
- (f) any incident that results in damage to an archaeological site or burial ground;
- (g) a significant disruption to authorized work or activities due to the carrying on of an activity, or the introduction into the environment of a substance, by a person unrelated to the project or power line;
- (h) an impairment to the reliability of the power system of the project or power line;
- (i) the impairment of any facility, equipment or system that is critical to safety, security or environmental protection or the impairment of a support craft;
- (j) any incident that results in the implementation of emergency response procedures. (incident Ă signaler)
- support craft
- means a vessel, vehicle, aircraft or other conveyance used to provide transportation or assistance to persons at an operations site. (véhicule de service)
- vessel
- has the same meaning as in section 2 of the Canada Shipping Act, 2001. (navire)
Incorporation by reference
2 (1) In these Regulations, any incorporation by reference of a document is an incorporation of that document as amended from time to time.
Bilingual document
(2) Despite subsection (1), if a document that is incorporated by reference is available in both official languages, any amendment to it is incorporated only when the amended version is available in both official languages.
General Requirements
Carrying on work or activities
3 For the purposes of subsection 298(2) of the Act, information submitted in an application for an authorization must demonstrate that the work or activities will be carried on in a manner that is safe and secure, that protects property and the environment, that is in conformity with all applicable laws in respect of safety, security and environmental protection and that takes into account the potential impacts of climate change.
Level of detail
4 The information submitted in support of an application and all documents and information submitted to the Regulator to meet a condition of an authorization must provide a level of detail that is proportionate to the scope, nature and complexity of the proposed work or activities.
PART 1
Offshore Renewable Energy — Wind Energy
Application
Application
5 This Part applies in respect of offshore renewable energy projects that exploit or aim to exploit the power of the wind to generate electricity and in respect of the offshore power lines associated with those projects.
Application for Authorization and Conditions of Authorization
Requirements for All Applications
Contents
6 For the purposes of subsection 298(2) of the Act, every application for authorization to carry on work or activities in relation to an offshore renewable energy project or offshore power line must include the following information and documents:
- (a) the name and contact information of the authorized representative of the operator;
- (b) the development concept for the project or power line as a whole, including any plans for overlapping or concurrent authorizations, for the proposed work or activities to be undertaken in stages or for the overall project or power line to be developed in stages;
- (c) a description of the work or activities that are the subject of the application, including
- (i) the objectives to be attained,
- (ii) the scope of the proposed work or activities, and
- (iii) maps or charts showing the preferred locations of all operations sites, as well as any other locations that are being considered;
- (d) a description of the anticipated use of support craft, of any other vessel, vehicle, aircraft or conveyance and of associated equipment and systems in carrying on the work or activities that are the subject of the application;
- (e) an execution plan and a schedule for undertaking the work or activities that are the subject of the application, including, if applicable, an indication of the need for any overlapping or concurrent authorizations or for the work or activities to be undertaken in stages;
- (f) if applicable, the results of
- (i) relevant surveys and monitoring programs, including those in respect of previously authorized work or activities in relation to the project or power line, and
- (ii) relevant analyses and assessments based on the data from such surveys and monitoring programs;
- (g) a description of how the results referred to in paragraph (f) were taken into account in the planning of the work or activities that are the subject of the application;
- (h) a description of the measures to be taken to conform with all applicable laws in relation to safety, security or environmental protection;
- (i) a description of the potential effects that the work or activities that are the subject of the application may have on any other users of the operations site;
- (j) a list of all the permits and other authorizations that are required in relation to the work or activities that are the subject of the application;
- (k) the target levels of safety, security and environmental protection that the operator proposes to establish under section 30 for the work or activities that are the subject of the application; and
- (l) if the operator is proposing to carry on the work or activities that are the subject of the application in a manner that differs from what was proposed in a previous application, a detailed description of the proposed changes, the rationale for those changes and a description of their effect.
Conditions of Every Authorization
System and plans
7 (1) For the purposes of subsection 298(9) of the Act, every authorization is subject to the condition that the operator, before the authorized work or activities begin, develop and implement
- (a) a management system that meets the requirements set out in section 8;
- (b) a safety plan that meets the requirements set out in section 9;
- (c) an environmental protection plan that meets the requirements set out in section 10; and
- (d) an emergency management plan that meets the requirements set out in section 11.
Submission and approval
(2) Every authorization is also subject to the condition that the operator submit the following information and plans to the Regulator and obtain the Regulator’s approval of the information referred to in paragraph (b) and the plans before the authorized work or activities begin:
- (a) the name, position and contact information of the accountable person designated under subsection 24(2);
- (b) a description of the management system, an explanation of how it has been implemented and a statement, signed by the accountable person, confirming that it has been implemented;
- (c) the safety plan;
- (d) the environmental protection plan; and
- (e) the emergency management plan.
Management system
8 (1) The management system must establish the overall framework for reducing risks to safety, security and the environment, including measures for ensuring the reliable operation of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line and for ensuring an appropriate response in case of an emergency.
Overarching requirements
(2) The management system must
- (a) be commensurate with the scope, nature and complexity of the authorized work or activities and the associated hazards and risks;
- (b) cover all of the authorized work or activities;
- (c) be explicit, comprehensive and proactive; and
- (d) foster a culture of safety.
Standards
(3) The management system must identify the management system standards on which it is based.
Contents
(4) The management system must include overarching policies, processes, procedures and protocols related to safety, security, environmental protection, the reliability of facilities, equipment and systems, and emergency response, including
- (a) processes for establishing and maintaining measurable goals and associated performance indicators for the management system;
- (b) processes for ensuring that persons who are assigned duties or who carry on authorized work or activities in relation to the offshore renewable energy project or offshore power line have the necessary experience, training, qualifications and competence, and receive the supervision that is necessary, for them to perform the duties or carry on the work or activities;
- (c) policies setting out the roles, responsibilities and authority of all persons performing functions under the management system, as well as processes for making them aware of their roles, responsibilities and authority;
- (d) processes for
- (i) identifying hazards that may arise during the authorized work or activities, including hazards related to human and organizational factors,
- (ii) assessing the risks associated with the identified hazards and determining the measures to be taken to minimize those risks,
- (iii) establishing an inventory of the identified hazards and the measures to be taken to minimize the associated risks, and
- (iv) keeping that inventory up to date;
- (e) processes for internally and externally communicating documents and information related to safety, security, environmental protection, the reliability of facilities, equipment and systems, and emergency response, including processes for informing persons who may be exposed to a hazard of the measures that will be taken to minimize the risks associated with the hazard;
- (f) processes for coordinating and managing the work of the operator, suppliers, service providers and other persons involved in carrying on the authorized work or activities, including processes for ensuring that the processes and procedures put in place by service providers are consistent with those put in place by the operator;
- (g) processes for auditing and evaluating the management system to ensure that it is functioning and achieving the measurable goals and associated performance indicators referred to in paragraph (a) and processes for ensuring that, if any deficiencies or areas for improvement are identified, the management system is updated to correct those deficiencies and make improvements;
- (h) processes for inspecting, monitoring, testing and maintaining all facilities, equipment and systems related to the offshore renewable energy project or offshore power line, including those set out in the integrity management program referred to in paragraph 18(a), if applicable, and processes for ensuring that, if any deficiencies or areas for improvement are identified, measures are taken to correct those deficiencies and make improvements;
- (i) processes for ensuring continuous improvement, including processes for
- (i) internally reporting hazards, reportable incidents and situations that have the potential to result in a reportable incident,
- (ii) analyzing the hazards, reportable incidents and situations and conducting investigations,
- (iii) identifying the root cause and causal factors of, and contributing factors to, the hazards, reportable incidents and situations, including any human or organizational factors,
- (iv) analyzing trends in respect of the hazards, reportable incidents and situations,
- (v) taking corrective and preventive measures, including measures to manage imminent hazards,
- (vi) providing feedback to persons who have made a report, and
- (vii) communicating documents and information concerning best practices or lessons learned from the hazards, reportable incidents and situations that might improve safety, security, environmental protection, the reliability of facilities, equipment and systems, and emergency response;
- (j) processes for identifying, evaluating and managing any changes that could affect safety, security, environmental protection, the reliability of facilities, equipment and systems, and emergency response;
- (k) processes for receiving information and fielding concerns related to safety, security and environmental protection from the general public and for reviewing and responding to such information and concerns;
- (l) processes for ensuring that all documents associated with the management system are approved by a person with the necessary authority, reviewed periodically and, if necessary, updated;
- (m) processes for ensuring that records associated with the management system and records that are necessary to support operational requirements or demonstrate compliance with all laws related to safety, security and environmental protection that apply in respect of the offshore renewable energy project or offshore power line are generated, classified by type, organized and retained and are readily accessible for consultation and examination by persons who require access to them; and
- (n) processes for monitoring compliance and preventing non-compliance with the conditions of the authorization and all laws related to safety, security and environmental protection that apply in respect of the offshore renewable energy project or offshore power line.
Safety plan
9 (1) The safety plan must set out the procedures, practices and resources, as well as the sequence of key safety-related activities, that are necessary to safely carry on the authorized work or activities and must include the following information:
- (a) a description of how the safety plan
- (i) integrates and reflects the processes and principles included in the management system that relate to safety, and
- (ii) ensures that the obligations set out in these Regulations with regard to safety are met;
- (b) a summary of the studies and a description of the processes used to
- (i) identify the safety hazards that may arise during the authorized work or activities, including any safety hazards that may arise due to activities taking place in the vicinity of the operations site, and
- (ii) assess the safety risks associated with the identified hazards;
- (c) a description of the hazards identified under subparagraph (b)(i) and the results of the risk assessment under subparagraph (b)(ii);
- (d) a description of the measures to be taken to anticipate, monitor, avoid and minimize the safety risks associated with the identified hazards, including, if hazards related to ice or icing are identified, measures for detecting, anticipating, monitoring and reporting those hazards, as well as measures for data collection and, if applicable, for ice avoidance or deflection;
- (e) an evaluation of the anticipated effectiveness of the measures referred to in paragraph (d) and of how they will assist in meeting the target levels of safety referred to in section 30;
- (f) a description of the methods that are to be used to communicate with persons who may be directly affected by the identified hazards regarding the existence of those hazards and the measures that will be taken to minimize the associated safety risks;
- (g) a description of all the facilities, equipment and systems that are critical to safety and are to be used during the authorized work or activities and a summary of the procedures and policies to be put in place for their inspection, testing and maintenance;
- (h) a detailed description of all support craft and other vessels, vehicles, aircraft or conveyances that are to be used;
- (i) a description of the training required by the persons who will carry on the authorized work or activities and the experience, qualifications and competencies that they must possess;
- (j) a description of the authorized work or activities that involve diving operations and the measures to be taken to ensure that those operations are carried out safely and in accordance with the prevailing industry standards and best practices that are appropriate for the water depth and type of diving involved;
- (k) a description of the measures to be taken to monitor compliance with the safety plan and to evaluate performance in relation to the plan’s objectives, including data collection and analysis, inspections and auditing;
- (l) a description of the organizational structure and the chain of command for ensuring that the authorized work or activities are carried on safely; and
- (m) a description of the processes to be put in place to identify, evaluate and manage any changes related to the authorized work or activities that could affect safety.
Service providers
(2) If the operator contracts for the provision of services with respect to the authorized work or activities, the safety plan must also include
- (a) a description of how the procurement process takes into consideration service providers’ past performance in relation to safety;
- (b) a description of service providers’ roles and responsibilities with respect to safety;
- (c) a description of the measures to be taken to oversee the work or activities of service providers and to ensure that service providers comply with the safety plan; and
- (d) a description of how the operator and service providers will communicate with each other regarding any safety issues that may arise during the work or activities.
Environmental protection plan
10 (1) The environmental protection plan must set out the procedures, practices and resources to be put in place to manage environmental hazards and protect the environment and must include the following information:
- (a) a description of how the environmental protection plan
- (i) integrates and reflects the processes and principles included in the management system that relate to environmental protection, and
- (ii) ensures that the obligations set out in these Regulations with regard to environmental protection are met;
- (b) a summary of the studies and a description of the processes used to
- (i) identify the environmental hazards that may arise during the authorized work or activities, including any environmental hazards that may arise due to activities taking place in the vicinity of the operations site, and
- (ii) assess the environmental risks associated with the identified hazards;
- (c) a description of the hazards identified under subparagraph (b)(i) and the results of the risk assessment under subparagraph (b)(ii);
- (d) the measures to be taken to anticipate, monitor, avoid and minimize the environmental risks associated with the identified hazards;
- (e) an evaluation of the anticipated effectiveness of the measures referred to in paragraph (d) and how they will assist in meeting the target levels of environmental protection referred to in section 30;
- (f) a description of the methods to be used to communicate with persons who may be directly affected by the identified hazards regarding the existence of those hazards and the measures that will be taken to minimize the associated environmental risks;
- (g) a description of all the facilities, equipment and systems that are critical to the protection of the environment and are to be used during the authorized work or activities and a summary of the procedures and policies to be put in place for their inspection, testing and maintenance;
- (h) a description of the organizational structure and the chain of command for ensuring that the authorized work or activities are carried on in a manner that minimizes environmental hazards;
- (i) a description of the procedure to be followed if an archaeological site or a burial ground is discovered during the authorized work or activities;
- (j) a description of the measures to be taken to monitor compliance with the environmental protection plan and to evaluate performance in relation to the plan’s objectives, including data collection and analysis, inspections and auditing; and
- (k) a description of the processes to be put in place to identify, evaluate and manage any changes related to the authorized work or activities that could affect the protection of the environment.
Service providers
(2) If the operator contracts for the provision of services with respect to the authorized work or activities, the environmental protection plan must also include
- (a) a description of how the procurement process takes into consideration service providers’ past performance in relation to environmental protection;
- (b) a description of service providers’ roles and responsibilities with respect to environmental protection;
- (c) a description of the measures to be taken to oversee the work or activities of service providers and to ensure that service providers comply with the environmental protection plan; and
- (d) a description of how the operator and service providers will communicate with each other regarding any environmental issues that may arise during the work or activities.
Emergency management plan
11 (1) The emergency management plan must set out the emergency response procedures referred to in subsection (2) and any other procedures, practices and resources that are necessary to effectively prepare for, manage and respond to an emergency and must include the following information:
- (a) a description of how the emergency management plan
- (i) integrates and reflects the processes and principles included in the management system that relate to emergency response, and
- (ii) ensures that the obligations set out in these Regulations with regard to emergency response are met;
- (b) a description of the types of incidents, in relation to the authorized work or activities, that may require an emergency response, an assessment of the risks associated with each type of incident and a description of the planned emergency response for each type of incident;
- (c) a description of the organizational structure and the chain of command for emergency response;
- (d) a method for classifying incidents;
- (e) a description of the incident management system to be used for emergency response;
- (f) a description of the methods that are to be used to monitor, constantly and in real time, both the facilities used in the generation and transmission of electrical energy and the work or activities, including at night and during periods of poor visibility;
- (g) the frequency and scope of the emergency response drills and exercises that are to be carried out to test and validate emergency response procedures and practices; and
- (h) a description of the measures that are to be taken to ensure that first responders, the personnel of relevant medical facilities, organizations and agencies, and persons that are carrying on activities within or in the vicinity of an operations site are informed of, and provided with instructions and updates concerning,
- (i) the location of the facilities that are to be used in the generation and transmission of electrical energy,
- (ii) the potential emergency situations that may arise in relation to those facilities, and
- (iii) the procedures to be followed in case of an emergency.
Emergency response procedures
(2) The emergency response procedures must cover the following subjects:
- (a) emergency response for each type of incident identified under paragraph (1)(b), including the emergency equipment that is necessary and is to be made available for emergency response to each type of incident;
- (b) the safe shutdown, in the event of an emergency, of facilities, equipment and systems to be used in the generation and transmission of electrical energy;
- (c) evacuation plans for personnel carrying on work or activities in the offshore area, including, if applicable, evacuation plans for divers engaged in a dive;
- (d) the notification, investigation and reporting of incidents under section 64;
- (e) the protocols for communicating with the relevant federal, provincial and municipal authorities and Indigenous governing bodies during an emergency response; and
- (f) coordination and liaison with all relevant emergency response organizations during an emergency response.
Site Assessment
Application — additional contents
12 For the purposes of subsection 298(2) of the Act, an application for authorization to carry on work or activities in relation to the site assessment for an offshore renewable energy project or offshore power line must include, in addition to the information and documents referred to in section 6,
- (a) a description of the surveys that are proposed to be conducted, including any seafloor hazard surveys and any biological, environmental, geological, geotechnical, geophysical, oceanographic, meteorological or archaeological surveys, as well as of any analyses or assessments to be performed using the data obtained from those surveys;
- (b) a description of the facilities, equipment and systems to be put in place for the site assessment, their proposed location, capabilities and limitations and, if any facilities, equipment or systems are to be installed on or moored to the seafloor, how they will be abandoned or removed;
- (c) a risk assessment in respect of the proposed work or activities that addresses the safety and security of persons and infrastructure that are at or in the vicinity of an operations site;
- (d) an environmental and socio-economic assessment in respect of the proposed work or activities; and
- (e) an assessment in respect of the proposed work or activities that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the Act.
Construction, Operation and Maintenance
Application — additional contents
13 For the purposes of subsection 298(2) of the Act, an application for authorization to carry on work or activities in relation to the construction, operation and maintenance of facilities, equipment and systems related to an offshore renewable energy project or offshore power line must include, in addition to the information and documents referred to in section 6,
- (a) a list of the industry standards and best practices to be used in the design of the facilities, equipment and systems, as well as any data sets to be used in establishing operational conditions and extreme loading conditions;
- (b) a description of the facilities, equipment and systems and their proposed location, capabilities and limitations, including, in the case of an offshore power line, maps that show
- (i) if applicable, the preferred location of each terminal point and each provincial interconnection point for the power line, as well as any other locations that are being considered,
- (ii) the preferred route for the power line, as well as any other routes that are being considered,
- (iii) constraints and hazards that restrict the preferred locations referred to in subparagraph (i) or the preferred route referred to in subparagraph (ii), and
- (iv) the width of the proposed corridor for the power line, accompanied by the reasons for the selected width;
- (c) a description of any existing infrastructure that was identified during the site assessment and an explanation of how that infrastructure was taken into account in the planning of the proposed work or activities;
- (d) a risk assessment in respect of the proposed work or activities for the construction, operation and maintenance of the facilities, equipment and systems, as well as the anticipated work or activities for their decommissioning and abandonment, that addresses the safety and security of persons and infrastructure that are at, on or in the vicinity of the facilities, equipment or systems, including an assessment of any risks associated with the operation of vessels, vehicles, aircraft or other conveyances in that vicinity;
- (e) an environmental and socio-economic assessment in respect of the proposed work or activities for the construction, operation and maintenance of the facilities, equipment and systems, as well as the anticipated work or activities for their decommissioning and abandonment;
- (f) an assessment in respect of the proposed work or activities for the construction, operation and maintenance of the facilities, equipment and systems, as well as the anticipated work or activities for their decommissioning and abandonment, that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the Act;
- (g) a description of the quality assurance program referred to in section 26 and an indication of the standard referred to in subsection 26(3) with which the program conforms;
- (h) the name of the organization that the operator proposes to engage as a certifying authority, a description of the organization’s qualifications to assume the responsibilities referred to in subsection 40(3) and the proposed general scope and timing of the activities to be carried out by the organization in relation to the issuance of a certificate of fitness under subsection 44(1);
- (i) an overview of the anticipated decommissioning and abandonment plan that will be submitted under paragraph 21(a); and
- (j) an estimate of the costs of the decommissioning and abandonment and an indication of the manner in which the operator will finance or pay for those costs.
Additional conditions — construction
14 For the purposes of subsection 298(9) of the Act, an authorization in relation to the construction, operation and maintenance of facilities, equipment and systems related to an offshore renewable energy project or offshore power line is, in addition to being subject to the conditions set out in section 7, subject to the condition that the operator ensure that the following documents and information are submitted to and approved by the Regulator before the authorized work or activities related to construction begin:
- (a) a facility design report that meets the requirements of section 15;
- (b) a fabrication and construction report that meets the requirements of section 16;
- (c) a facilities reliability report that meets the requirements of section 17;
- (d) a description of a preliminary version of the integrity management program that will be submitted under paragraph 18(a);
- (e) a description of the navigational safety zones proposed for the purposes of paragraph 28(1)(a) or a justification of why navigational safety zones are not needed; and
- (f) the plan referred to in section 45, prepared by the certifying authority, for the periodic inspection of the facilities, equipment and systems during their construction.
Facility design report
15 (1) The facility design report must contain a comprehensive description of the design of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line that are outlined in the authorization, including
- (a) a summary of the engineering design criteria and data;
- (b) a summary of the physical and environmental data used in analyzing the design of the facilities, equipment and systems;
- (c) front, side and plan view technical drawings of the facilities;
- (d) a list of the industry standards and best practices used in the design of the facilities, equipment and systems, as well as any data sets used in establishing operational conditions and extreme loading conditions;
- (e) a complete set of structural drawings to be used for the fabrication and construction of the facilities, equipment and systems;
- (f) the target levels of safety, security and environmental protection referred to in section 30;
- (g) a copy of the studies used in designing the facilities, equipment and systems and planning their installation;
- (h) a description of the loads that will be imposed on the facilities;
- (i) detailed information on
- (i) the structural integrity of facilities, and
- (ii) the stability and motion response characteristics of any floating infrastructure;
- (j) a description of the major mechanical components to be used in the facilities, equipment and systems, including design drawings that illustrate and identify each of those components;
- (k) a description of the major electrical components to be used in the facilities, equipment and systems, including a single-line diagram that illustrates and identifies each of those components;
- (l) a description of the measures, including the markings, lighting and signalling, to be put in place to identify the facilities, equipment and systems, warn any vessels, vehicles, aircraft and other conveyances operating in the vicinity of the facilities, equipment and systems of their presence and prevent any collisions, including in reduced visibility conditions; and
- (m) an indication of the anticipated design life of the facilities, equipment and systems, as well as that of their significant components.
Additional requirements
(2) The facility design report must also
- (a) demonstrate that the design conforms with all applicable laws and the conditions of the authorization;
- (b) demonstrate that the design is in keeping with any information provided and any approach, methodology or technology proposed in an application in respect of any previously authorized work or activities in relation to the offshore renewable energy project or offshore power line; and
- (c) include the certification statement referred to in paragraph 40(3)(a).
Fabrication and construction report
16 (1) The fabrication and construction report must contain a comprehensive description of how the facilities, equipment and systems related to the offshore renewable energy project or offshore power line are to be fabricated, transported, constructed and installed, including
- (a) a schedule for the authorized work or activities related to the fabrication and construction of the facilities, equipment and systems;
- (b) a list of the prevailing industry standards and best practices to be followed to ensure that the facilities, equipment and systems are fabricated and constructed according to the design set out in the facility design report;
- (c) detailed information about how fabricated components are to be transported to the operations site and installed, including a description of the vessels, equipment, systems and, if applicable, anchoring and mooring arrangements to be used; and
- (d) information concerning the methods and vessels to be used to bury or otherwise protect cables or pipelines, if applicable.
Additional requirements
(2) The fabrication and construction report must also
- (a) demonstrate that the fabrication and construction will conform with
- (i) all applicable laws,
- (ii) the conditions of the authorization,
- (iii) the design set out in the facility design report, and
- (iv) prevailing industry standards and best practices;
- (b) demonstrate that the fabrication and construction will be in keeping with any information provided and any approach, methodology or technology proposed in an application in respect of previously authorized work or activities in relation to the offshore renewable energy project or the offshore power line; and
- (c) include the certification statement referred to in paragraph 40(3)(b).
Facilities reliability report
17 (1) The facilities reliability report must describe
- (a) the measures to be taken to ensure the reliability of the power system related to the offshore renewable energy project and associated offshore power lines;
- (b) the impacts that the project and associated power lines will have on the bulk power system;
- (c) the anticipated maximum power transfer capabilities of the project and associated power lines under both winter and summer conditions, the criteria used to determine those capabilities and the mitigation measures to be taken in the event of severe weather conditions; and
- (d) the reliability standards to which the project and associated power lines will be subject during operation.
Additional requirement
(2) The facilities reliability report must also demonstrate that the measures referred to in paragraph (1)(a) are in conformity with all applicable laws and the conditions of the authorization.
Additional conditions — operation and maintenance
18 For the purposes of subsection 298(9) of the Act, an authorization in relation to the construction, operation and maintenance of facilities, equipment and systems related to an offshore renewable energy project or offshore power line is, in addition to being subject to the conditions set out in sections 7 and 14, subject to the condition that the operator ensure that the following documents and information are submitted to and approved by the Regulator before the authorized work or activities related to operation and maintenance begin:
- (a) a description of the finalized version of an integrity management program that meets the requirements set out in section 19;
- (b) a preliminary version of the decommissioning and abandonment plan that will be submitted under paragraph 21(a) that builds on the overview referred to in paragraph 13(i);
- (c) any updates to the information provided under paragraph 13(j);
- (d) a description of the navigational safety zones proposed for the purposes of paragraph 28(1)(a) or a justification of why navigational safety zones are not needed;
- (e) the certificate of fitness issued under subsection 44(1) in respect of the facilities, equipment and systems; and
- (f) the plan referred to in section 45, prepared by the certifying authority, for the periodic inspection of the facilities, equipment and systems during their operation and maintenance.
Integrity management program
19 (1) The integrity management program must be aimed at ensuring that all facilities, equipment and systems related to the offshore renewable energy project or offshore power line
- (a) meet the requirements of all applicable laws in respect of the design of such facilities, equipment and systems;
- (b) are tested, inspected, monitored, maintained and operated in such a way as to ensure safety, security and environmental protection under the operating conditions and maximum loads that are likely to exist during any authorized work or activities; and
- (c) remain fit for the purposes for which they are to be used and can be operated without posing a threat to safety, security or the environment.
Risk assessment
(2) The integrity management program must be based on a risk assessment that is conducted in accordance with industry best practices and that takes into account the assumptions on which the design is based.
Monitoring, inspection and testing
(3) The integrity management program must set out the measures to be taken by the operator to monitor the condition of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line and to conduct periodic inspections and testing, and must include
- (a) the measures to be taken to evaluate the condition of the facilities, equipment and systems and the operational, physical and environmental conditions to which they are subjected;
- (b) the scope and frequency of the periodic inspections that are necessary to ensure the continued performance and safe functioning of the facilities, equipment and systems;
- (c) a description of the incidents, including natural events and accidents, that will trigger an inspection; and
- (d) the scope of the inspection to be conducted after an incident occurs.
Additional requirement
(4) The finalized version of the integrity management program must also include the certification statement referred to in paragraph 40(3)(c).
Documentation of results
(5) The operator must document the results of the monitoring, inspection and testing carried out for the purposes of the integrity management program.
Decommissioning and Abandonment
Application — additional contents
20 For the purposes of subsection 298(2) of the Act, an application for authorization to carry on work or activities in relation to the decommissioning and abandonment of facilities, equipment and systems related to an offshore renewable energy project or offshore power line must include, in addition to the information and documents referred to in section 6,
- (a) a description of any existing infrastructure at the operations site and an explanation of how that infrastructure was taken into account in the planning of the work or activities that are the subject of the application;
- (b) the results of an assessment of the condition of any facilities, equipment or systems that are to be decommissioned and abandoned;
- (c) a description of the facilities, equipment and systems to be decommissioned and abandoned in place or decommissioned, removed and disposed of, as the case may be, including, if applicable, the methods to be used to remove and transport them and how and where they are to be disposed of;
- (d) a risk assessment in respect of the work or activities that are the subject of the application that addresses the safety and security of persons and infrastructure that are at, on or in the vicinity of the facilities, equipment or systems, including an assessment of any risks associated with the operation of vessels, vehicles, aircraft or other conveyances in that vicinity;
- (e) an environmental and socio-economic assessment in respect of the work or activities that are the subject of the application;
- (f) an assessment in respect of the work or activities that are the subject of the application that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the Act;
- (g) a description of the methods to be used to restore the operations site after the decommissioning and abandonment of the facilities, equipment and systems; and
- (h) an estimate of the costs of the decommissioning and abandonment and an indication of the manner in which the operator will finance or pay for those costs.
Additional conditions — decommissioning and abandonment
21 For the purposes of subsection 298(9) of the Act, an authorization in relation to the decommissioning and abandonment of facilities, equipment and systems related to an offshore renewable energy project or offshore power line is, in addition to being subject to the conditions set out in section 7, subject to the condition that the operator ensure that the following document and information are submitted to and approved by the Regulator before the authorized work or activities related to decommissioning and abandonment begin:
- (a) a detailed finalized decommissioning and abandonment plan in respect of the facilities, equipment and systems that meets the requirements set out in section 22; and
- (b) a description of the navigational safety zones proposed for the purposes of paragraph 28(1)(a) or a justification of why navigational safety zones are not needed.
Decommissioning and abandonment plan
22 The decommissioning and abandonment plan must include the following information:
- (a) the proposed approach for decommissioning and abandoning the facilities, equipment and systems related to the offshore renewable energy project or offshore power line, including details regarding their removal, transportation and disposal, if applicable;
- (b) a description of the safety, security and environmental protection measures to be implemented during the decommissioning and abandonment to ensure compliance with all applicable laws;
- (c) a description of the potential effects that the decommissioning and abandonment will have on the environment and on other users of the operations site; and
- (d) the methods to be used to restore the operations site after the decommissioning and abandonment.
General Requirements for Operators
Management System and Associated Plans
Implementation
23 (1) The operator must continue to implement the management system, safety plan, environmental protection plan and emergency management plan referred to in section 7 for the entire duration of the authorized work or activities in relation to the offshore renewable energy project or offshore power line.
Updates
(2) The operator must ensure that the management system, safety plan, environmental protection plan and emergency management plan are updated periodically to ensure that they continue to meet the requirements set out in sections 8, 9, 10 and 11, respectively.
Financial and human resources
24 (1) The operator must ensure that there are sufficient financial and human resources to implement and continually improve the management system, safety plan, environmental protection plan and emergency management plan.
Accountable person
(2) The operator must designate one of its employees as the accountable person for the management system, safety plan, environmental protection plan and emergency management plan and ensure that the accountable person has the necessary authority for assigning financial and human resources to develop, implement and make ongoing improvements to that system and those plans.
Change — accountable person
(3) If there is any change to the name, position or contact information of the accountable person that was submitted under paragraph 7(2)(a), the operator must provide updated information to the Regulator as soon as feasible.
Integrity Management Program and Quality Assurance Program
Integrity management program
25 (1) The operator must implement the integrity management program referred to in paragraph 18(a) for the entire duration of the authorized work or activities in relation to the operation and maintenance of the offshore renewable energy project or offshore power line.
Updates
(2) The operator must ensure that the integrity management program is updated periodically so that it continues to meet the requirements set out in section 19.
Quality assurance program
26 (1) The operator must develop a quality assurance program in respect of the fabrication, transportation, installation and commissioning of all facilities, equipment and systems related to the offshore renewable energy project or offshore power line and any components used in the maintenance of those facilities, equipment and systems.
Requirements
(2) The quality assurance program must be comprehensive and must set out the requirements for monitoring, documenting and managing quality to ensure that the facilities, equipment and systems are fit for the purposes for which they are to be used.
Conformity with recognized standard
(3) The quality assurance program must be in conformity with a recognized Canadian or international standard for quality management.
Implementation
(4) The operator must implement the quality assurance program for the entire duration of the authorized work or activities other than work or activities related to site assessment.
Updates
(5) The operator must ensure that the quality assurance program is updated periodically.
Other Requirements
Carrying on of authorized work or activities
27 (1) The operator must carry on all authorized work or activities in a manner that ensures safety, security and environmental protection by
- (a) meeting the requirements of the management system, safety plan, environmental protection plan, emergency management plan, integrity management program and quality assurance program and ensuring that all employees, suppliers, service providers and other persons involved in the authorized work or activities meet those requirements;
- (b) respecting any limitations set out in the certificate of fitness issued in relation to the operation of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line to ensure that their operation does not pose a threat to safety, security or the environment;
- (c) monitoring the compliance of employees, suppliers, service providers and other persons involved in the authorized work or activities with all conditions of authorization;
- (d) ensuring the safe and reliable operation of facilities, equipment and systems related to the offshore renewable energy project or offshore power line;
- (e) taking all reasonable measures to minimize damage to property;
- (f) taking all reasonable measures to minimize adverse effects for other persons in the offshore area;
- (g) using the best available technologies for mitigating adverse effects on persons and the environment that are economically feasible to implement;
- (h) complying with prevailing industry standards and best practices;
- (i) taking all reasonable measures to prevent debris and to prevent or, if prevention is not possible, minimize the introduction into the environment of any substance or form of energy that is likely to have an adverse effect on the environment; and
- (j) taking all reasonable measures to minimize any adverse effects on persons and the environment when restoring the operations site after the decommissioning and abandonment of the facilities, equipment and systems.
Equipment and systems
(2) The operator must ensure that
- (a) all equipment and systems that are used during the authorized work or activities are tested, inspected, maintained, operated and handled in such a way as to ensure safety, security and environmental protection, taking into consideration the manufacturer’s instructions and any applicable standards; and
- (b) any defective components of the equipment or systems are promptly repaired or replaced, taking into consideration the manufacturer’s instructions and any applicable standards.
Assignment of duties
(3) The operator must ensure that persons who are assigned duties or who carry on authorized work or activities
- (a) have the necessary experience, training, qualifications and competence to perform the duties or carry on the work or activities in accordance with these Regulations and in a manner that ensures safety, security and environmental protection; and
- (b) are sufficient in number and receive the supervision that is necessary for them to perform the duties or carry on the work or activities in a manner that ensures safety, security and environmental protection.
Navigational safety zones
28 (1) The operator must take measures to protect facilities, equipment and systems at an operations site against collision with vessels, vehicles, aircraft and other conveyances operating in the vicinity of the facilities, equipment and systems from the time their construction begins until their decommissioning and abandonment is completed, including by
- (a) establishing the navigational safety zones referred to in paragraph 14(e), 18(d) or 21(b), as the case may be, that are approved by the Regulator; and
- (b) ensuring that the following information is made available to other persons in the offshore area and brought to the attention of the Canadian Coast Guard, the Department of Transport and the Canadian Hydrographic Service of the Department of Fisheries and Oceans:
- (i) the location of the operations site and of the facilities, equipment and systems,
- (ii) the boundaries of the navigational safety zones, and
- (iii) a description of the risks associated with navigation in the vicinity of the facilities, equipment and systems.
Boundaries of navigational safety zone
(2) The establishment of the boundaries of a navigational safety zone must be informed by the risk assessment referred to in paragraph 13(d) or 20(d) as it relates to the risks associated with navigation in the vicinity of the facilities, equipment or systems at the operations site, but the distance between the outer extremity of the facilities, equipment or systems and the perimeter of the safety zone must not exceed 500 m in any direction, except as permitted under paragraph 5 of Article 60 of Part V of the United Nations Convention on the Law of the Sea.
Routing systems and measures
(3) A navigational safety zone must not interfere with the use of established routing systems and routing measures related to navigational safety.
Design requirements
29 (1) The operator must ensure that all facilities, equipment and systems related to the offshore renewable energy project or offshore power line are designed
- (a) in such a way as to ensure safety, security and environmental protection, including by achieving the target levels of safety, security and environmental protection established under section 30;
- (b) using the best available technologies for minimizing adverse effects on persons, infrastructure and the environment that are economically feasible to implement; and
- (c) in accordance with prevailing industry standards and best practices.
Factors to be taken into account
(2) The design of the facilities, equipment and systems must take into account their intended use, their location and any site-specific physical and environmental conditions.
Physical and environmental conditions
(3) The operator must ensure that every facility related to the offshore renewable energy project or offshore power line is designed to withstand or avoid all reasonably foreseeable site-specific physical and environmental conditions, including any reasonably foreseeable combination of those conditions, without its structural integrity or any associated equipment or systems that are critical to safety, security and environmental protection being compromised.
Target levels
30 (1) The operator must establish measurable target levels of safety, security and environmental protection for each work or activity carried on in relation to the offshore renewable energy project or offshore power line.
Quantitative or qualitative assessment
(2) The target levels of safety, security and environmental protection must be based on a quantitative assessment unless quantitative assessment methods are inappropriate or the quantitative data is not reliable, in which case the target levels must be based on a qualitative assessment.
Critical software
31 (1) The operator must ensure that any software that is critical to safety, security or environmental protection is
- (a) secure, reliable and capable of being updated;
- (b) designed, commissioned and updated in a competent manner; and
- (c) demonstrated to be fit for the purposes for which it is to be used through a testing and validation process that takes into consideration
- (i) all foreseeable operating conditions and emergency situations, and
- (ii) system complexity, the dependencies and interactions among systems, software failure modes and the level of risk associated with system failure or malfunction.
Modifications to software features
(2) The features of the software referred to in subsection (1) must not be modified unless the necessary internal approvals for the modification are obtained, including the approval of the facility manager.
Testing and validation
(3) The modified software must not be used until it has been tested and validated in accordance with paragraph (1)(c).
Software-dependent control systems
32 If the failure or malfunction of any integrated software-dependent control systems would cause a hazard to safety, security or the environment, the operator must ensure that
- (a) the control systems are designed, installed, commissioned and maintained in such a way as to ensure their reliability, availability and security; and
- (b) measures are implemented and maintained to protect the control systems from any threat, including unauthorized access.
Rescue boat
33 The operator must ensure that a rescue boat is available and ready for use in the event of an emergency at all times when personnel are present in the offshore area for the purposes of carrying on authorized work or activities.
Requirements for vessels
34 The operator must ensure that every vessel that is used to carry on authorized work or activities is suitable for the operations site at which it is used and for the nature of the work or activities.
Evacuation systems and equipment
35 In determining the number of persons that any lifeboat, life raft or marine evacuation system can accommodate, the operator must take into consideration each person’s weight while the person is wearing an immersion suit, as well as the space they require while wearing such a suit.
Third-party assessment
36 The operator must ensure that a competent third party verifies all equipment that is installed temporarily on a vessel that is used in connection with any authorized work or activities to ensure that the equipment is fit for the purpose for which it is to be used and is secured in a seaworthy manner.
Landing area
37 (1) If personnel will be transported by aircraft to or within an operations site or between operations sites, the operator must ensure that the landing area for the aircraft, or for any person or cargo being raised to or lowered from the aircraft, is designed to ensure safety, security and environmental protection, including the prevention of incidents or damage due to the use of an aircraft.
Specific requirements
(2) The operator must ensure that the landing area
- (a) does not contain any obstacles that may impede the safe landing or takeoff of aircraft or the safe disembarkation or embarkation of persons or cargo and, if applicable, is oriented relative to the prevailing winds;
- (b) is able to withstand all functional loads that may be imposed on it;
- (c) has conspicuous markings and signage; and
- (d) has adequate lighting, including for reduced visibility conditions.
Specific requirements — landing and takeoff
(3) The operator must ensure that any area used for the landing or takeoff of aircraft is capable of accommodating aircraft of expected sizes and is equipped with
- (a) emergency response and firefighting equipment;
- (b) a monitoring system and status light system;
- (c) communication and meteorological equipment; and
- (d) if the landing area is on a facility, fuel storage tanks.
Procedures and training program
38 (1) The operator must ensure that
- (a) procedures with respect to the support of aircraft operations, including procedures for emergency response, are developed and implemented; and
- (b) a training program is provided for personnel and passengers in respect of those procedures.
Aircraft service provider
(2) Before any authorized work or activities that require the use of an aircraft begin, the operator must ensure that the aircraft service provider has accepted in writing to
- (a) comply with all conditions stipulated by the operator with respect to the use of the equipment on any landing area;
- (b) implement the procedures referred to in paragraph (1)(a); and
- (c) ensure that all personnel and passengers follow the training program referred to in paragraph (1)(b).
Access to documents and information
39 The operator must ensure that a copy of the following documents and information is readily accessible at each operations site when personnel are present and at all times at every associated control centre and emergency response operations centre:
- (a) every authorization issued in respect of work or activities related to the offshore renewable energy project or offshore power line;
- (b) all information and documents submitted to the Regulator to meet a condition of authorization, including the safety plan, environmental protection plan and emergency management plan, as well as supporting documentation; and
- (c) all procedures and other documents that are necessary to carry on authorized work or activities in a manner that ensures safety, security and environmental protection.
Certifying Authority and Certificate of Fitness
Certifying authority
40 (1) The operator must engage the services of an organization to serve as a certifying authority.
Approval by Regulator
(2) The organization engaged by the operator must be approved as a certifying authority by the Regulator based on the organization’s qualifications to assume the responsibilities referred to in subsection (3).
Responsibilities of certifying authority
(3) The certifying authority is responsible for
- (a) conducting an independent assessment of the facility design report referred to in paragraph 14(a), including an assessment of the design inputs, the methodologies used in the design and the results of any technical studies undertaken in support of the design, and providing a certification statement to the operator that confirms that the proposed design of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line is in accordance with good engineering practices, the authorization and all applicable laws;
- (b) conducting an independent assessment of the fabrication and construction report referred to in paragraph 14(b) and providing a certification statement to the operator that confirms that the proposed fabrication, construction and installation of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line are in accordance with good engineering practices, the authorization and all applicable laws;
- (c) conducting an independent assessment of the integrity management program referred to in paragraph 18(a) and providing a certification statement to the operator that confirms that the proposed measures to ensure the integrity of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line are in accordance with good engineering practices, the authorization and all applicable laws;
- (d) monitoring and carrying out inspections related to the fabrication, transportation, construction, installation and commissioning of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line, including any major maintenance or modifications;
- (e) assessing whether the facilities, equipment and systems related to the offshore renewable energy project or offshore power line have been fabricated, constructed and installed in accordance with
- (i) good engineering practices,
- (ii) the fabrication and construction report referred to in paragraph 14(b), and
- (iii) the authorization;
- (f) verifying that the facilities, equipment and systems related to the offshore renewable energy project or offshore power line are fit for the purposes for which they are to be used and can be operated without posing a threat to safety, security or the environment;
- (g) issuing a certificate of fitness in respect of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line;
- (h) periodically performing on-site or remote inspections of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line to verify their continued integrity in accordance with the integrity management program referred to in paragraph 18(a) and ensure that they remain fit for the purposes for which they are to be used and can be operated without posing a threat to safety, security or the environment;
- (i) validating the effectiveness of any measures implemented by the operator to minimize risks in relation to safety, security and the environment that are associated with the facilities, equipment and systems related to the offshore renewable energy project or offshore power line; and
- (j) verifying that the certificate of fitness remains valid for as long as the facilities, equipment and systems related to the offshore renewable energy project or offshore power line remain in operation.
Operator’s obligations
41 The operator must ensure that
- (a) the certifying authority has, for the purpose of fullfilling its responsibilities, access to the facilities, equipment and systems related to the offshore renewable energy project or offshore power line, as well as to the necessary documentation; and
- (b) the certificate of fitness issued under subsection 44(1) remains valid for as long as the facilities, equipment and systems remain in operation.
Scope of work
42 The certifying authority must submit a scope of work to the Regulator for approval and obtain the Regulator’s approval before undertaking the relevant activities referred to in subsection 40(3) in relation to the construction, operation and maintenance of the facilities, equipment and systems related to an offshore renewable energy project or offshore power line.
Performance of functions
43 In performing its functions, the certifying authority must
- (a) carry out the scope of work that was approved by the Regulator;
- (b) use good engineering judgment and practices; and
- (c) ensure that any person that is tasked with carrying out an activity referred to in subsection 40(3) has the necessary experience, training, qualifications and competence to do so.
Certificate of fitness
44 (1) The certifying authority may, on the basis of the activities referred to in subsection 40(3), issue a certificate of fitness in respect of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line.
Fitness for purpose
(2) The certificate of fitness must confirm that the facilities, equipment and systems are fit for the purposes for which they are to be used and can be operated without posing a threat to safety, security or the environment.
Limitations on operation
(3) The certificate of fitness may set out limitations in relation to the operation of the facilities, equipment and systems that the certifying authority considers necessary to ensure that their operation does not pose a threat to safety, security or the environment.
Copy provided to Regulator
(4) The certifying authority must provide a copy of the certificate of fitness to the Regulator.
Inspection plans
45 (1) The certifying authority must prepare a plan for the periodic inspection of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line during their construction and during their operation and maintenance and provide those plans to the Regulator.
Review of operator’s records
(2) The inspection plan must
- (a) include a schedule for the periodic review of the operator’s records from the management system to identify any changes to the management system that might affect safety, security or environmental protection; and
- (b) be updated as needed to ensure that the facilities, equipment and systems are inspected in light of those changes.
Scope and frequency of inspections
(3) The certifying authority must establish the scope and frequency of the periodic inspections based on a risk assessment conducted in accordance with prevailing industry standards and best practices.
Changes to inspection plan
(4) The certifying authority must, as soon as circumstances permit, inform the Regulator of any material changes to the inspection plan.
Independence and impartiality
46 (1) The certifying authority must not issue a certificate of fitness in respect of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line unless the certifying authority is able to fulfill its responsibilities under subsection 40(3) with independence and impartiality, including by ensuring that
- (a) a separation is maintained between the certification functions that it or any of its subsidiaries or affiliates perform and any work that it or any of its subsidiaries or affiliates undertake with respect to the design, construction, transportation, installation, establishment or commissioning of the facilities, equipment and systems; and
- (b) barriers and processes are in place to prevent real, potential or perceived conflicts of interest.
Notification of conflict of interest
(2) The certifying authority must monitor for real, potential or perceived conflicts of interest throughout the period that it acts as certifying authority for the operator and must, without delay, notify the operator and the Regulator of any such conflicts that are identified.
Change of certifying authority
47 (1) If the operator decides to replace the certifying authority with a new certifying authority, the operator must provide the name of the organization that the operator proposes to engage as the new certifying authority to the Regulator, along with a description of the organization’s qualifications to assume the responsibilities referred to in subsection 40(3).
Before issuance of certificate
(2) If the operator engages a new certifying authority before the initial certificate of fitness is issued, the new certifying authority must carry out its own independent assessment, monitoring, inspection, verification and validation activities for the purposes of issuing the certificate.
After issuance of certificate
(3) If the operator engages a new certifying authority after a certificate of fitness has been issued, the operator must develop and submit to the Regulator a transition plan outlining all of the activities to be carried out by the parties before the transition from the former to the new certifying authority and demonstrating that the transition will not result in any gaps, delays or negative effects on the extent and quality of the activities referred to in subsection 40(3).
Implementation of transition plan
(4) The operator must ensure that the transition plan is implemented.
One certificate and one authority
(5) There must be no more than one certificate of fitness and one certifying authority in relation to an offshore renewable energy project or offshore power line at any given time.
Annual report
48 Within 30 days after the end of each calendar year during which authorized work or activities are carried on in relation to the construction, operation and maintenance of facilities, equipment and systems related to the offshore renewable energy project or offshore power line, the certifying authority must submit a report for that year to the Regulator that includes
- (a) an overview of the activities that it carried out during the calendar year in its capacity as certifying authority;
- (b) a statement, signed by the certifying authority, confirming that it has maintained the qualifications it possessed when it was approved by the Regulator as a certifying authority;
- (c) the name, position, contact information and qualifications of the persons that were involved in carrying out the activities referred to in subsection 40(3);
- (d) if applicable, a description of the methodologies used to conduct the independent assessments referred to in paragraphs 40(3)(a) to (c) and the assessment referred to in paragraph 40(3)(e) and the results of those assessments;
- (e) a detailed description of the inspections performed during the calendar year, including their scope and the methodology used, as well as the results;
- (f) a description of the activities that it carried out to validate the effectiveness of any measures implemented by the operator to minimize risks in relation to safety, security and the environment and the results of that validation.
PART 2
Offshore Renewable Energy — Other Than Wind Energy
Application
Application
49 This Part applies in respect of offshore renewable energy projects — other than those that exploit or aim to exploit the power of the wind to generate electricity — and the offshore power lines associated with those projects.
Requirements for All Applications
Contents
50 For the purposes of subsection 298(2) of the Act, every application for authorization to carry on work or activities in relation to an offshore renewable energy project or offshore power line must include the following information and documents:
- (a) the name and contact information of the authorized representative of the operator;
- (b) the development concept for the project or power line as a whole, including any plans for overlapping or concurrent authorizations, for the proposed work or activities to be undertaken in stages or for the overall project or power line to be developed in stages;
- (c) a description of the work or activities that are the subject of the application, including
- (i) the objectives to be attained,
- (ii) the scope of the proposed work or activities, and
- (iii) maps or charts showing the preferred locations of all operations sites, as well as any other locations that are being considered;
- (d) a description of the anticipated use of support craft, of any other vessel, vehicle, aircraft or conveyance and of associated equipment and systems in carrying on the work or activities that are the subject of the application;
- (e) an execution plan and a schedule for undertaking the work or activities that are the subject of the application, including, if applicable, an indication of the need for any overlapping or concurrent authorizations or for the work or activities to be undertaken in stages;
- (f) if applicable, the results of
- (i) relevant surveys and monitoring programs, including those in respect of previously authorized work or activities in relation to the project or power line, and
- (ii) relevant analyses and assessments based on the data from such surveys and monitoring programs;
- (g) a description of how the results referred to in paragraph (f) were taken into account in the planning of the work or activities that are the subject of the application;
- (h) a description of the measures to be taken to conform with all applicable laws in relation to safety, security or environmental protection;
- (i) a description of the potential effects that the work or activities that are the subject of the application may have on any other users of the operations site;
- (j) a list of all the permits and other authorizations that are required in relation to the work or activities that are the subject of the application;
- (k) if the operator is proposing to carry on the work or activities that are the subject of the application in a manner that differs from what was proposed in a previous application, a detailed description of the proposed changes, the rationale for those changes and a description of their effect;
- (l) a risk assessment in respect of the proposed work or activities that addresses the safety and security of persons and infrastructure that are at or in the vicinity of an operations site;
- (m) an environmental and socio-economic assessment in respect of the proposed work or activities;
- (n) an assessment in respect of the proposed work or activities that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the Act;
- (o) a list of the industry standards and best practices to be used in the design of the facilities, equipment and systems that are to be used in the generation and transmission of electrical energy, as well as any data sets to be used in establishing operational conditions and extreme loading conditions;
- (p) a description of the facilities, equipment and systems that are to be used in the generation and transmission of electrical energy and their proposed location, capabilities and limitations, including, in the case of an offshore power line, maps that show
- (i) if applicable, the preferred location of each terminal point and each provincial interconnection point for the power line, as well as any other locations that are being considered,
- (ii) the preferred route for the power line, as well as any other routes that are being considered,
- (iii) constraints and hazards that restrict the preferred locations referred to in subparagraph (i) or the preferred route referred to in subparagraph (ii), and
- (iv) the width of the proposed corridor for the power line, accompanied by the reasons for the selected width; and
- (q) the proposed approach to the decommissioning and abandonment of the facilities, equipment and systems related to the project or power line, an estimate of the costs of the decommissioning and abandonment and an indication of the manner in which the operator will finance or pay for those costs.
Conditions of Every Authorization
Plans
51 (1) For the purposes of subsection 298(9) of the Act, every authorization is subject to the condition that the operator, before the authorized work or activities begin, develop and implement
- (a) a safety plan that meets the requirements set out in section 52;
- (b) an environmental protection plan that meets the requirements set out in section 53; and
- (c) an emergency management plan that meets the requirements set out in section 54.
Submission and approval
(2) Every authorization is also subject to the condition that the operator submit the following information and plans to the Regulator and obtain the Regulator’s approval of the information referred to in paragraph (e) and the plans before the authorized work or activities begin:
- (a) the name, position and contact information of the accountable person designated under subsection 55(2);
- (b) the safety plan;
- (c) the environmental protection plan;
- (d) the emergency management plan; and
- (e) a description of the navigational safety zones proposed for the purposes of paragraph 57(1)(a) or a justification of why navigational safety zones are not needed.
Safety plan
52 (1) The safety plan must set out the procedures, practices and resources , as well as the sequence of key safety-related activities, that are necessary to safely carry on the authorized work or activities and must include the following information:
- (a) a description of how the safety plan ensures that the obligations set out in these Regulations with regard to safety are met;
- (b) a summary of the studies and a description of the processes used to
- (i) identify the safety hazards that may arise during the authorized work or activities, including any safety hazards that may arise due to activities taking place in the vicinity of the operations site, and
- (ii) assess the safety risks associated with the identified hazards;
- (c) a description of the hazards identified under subparagraph (b)(i) and the results of the risk assessment under subparagraph (b)(ii);
- (d) a description of the measures to be taken to anticipate, monitor, avoid and minimize the safety risks associated with the identified hazards, including, if hazards related to ice or icing are identified, measures for detecting, anticipating, monitoring and reporting those hazards, as well as measures for data collection and, if applicable, for ice avoidance or deflection;
- (e) an evaluation of the anticipated effectiveness of the measures referred to in paragraph (d);
- (f) a description of the methods to be used to communicate with persons who may be directly affected by the identified hazards regarding the existence of those hazards and the measures that will be taken to minimize the associated safety risks;
- (g) a description of all the facilities, equipment and systems that are critical to safety and are to be used during the authorized work or activities and a summary of the procedures and policies to be put in place for their inspection, testing and maintenance;
- (h) a detailed description of all support craft and other vessels, vehicles, aircraft or conveyances that are to be used;
- (i) a description of the training required by the persons who will carry on the authorized work or activities and the experience, qualifications and competencies that they must possess;
- (j) a description of the authorized work or activities that involve diving operations and the measures to be taken to ensure that those operations are carried out safely and in accordance with the prevailing industry standards and best practices that are appropriate for the water depth and type of diving involved;
- (k) a description of the measures to be taken to monitor compliance with the safety plan and to evaluate performance in relation to the plan’s objectives, including data collection and analysis, inspections and auditing;
- (l) a description of the organizational structure and the chain of command for ensuring that the authorized work or activities are carried on safely; and
- (m) a description of the processes to be put in place to identify, evaluate and manage any changes related to the authorized work or activities that could affect safety.
Service providers
(2) If the operator contracts for the provision of services with respect to the authorized work or activities, the safety plan must also include
- (a) a description of how the procurement process takes into consideration service providers’ past performance in relation to safety;
- (b) a description of service providers’ roles and responsibilities with respect to safety;
- (c) a description of the measures to be taken to oversee the work or activities of service providers and to ensure that service providers comply with the safety plan; and
- (d) a description of how the operator and service providers will communicate with each other regarding any safety issues that may arise during the work or activities.
Environmental protection plan
53 (1) The environmental protection plan must set out the procedures, practices and resources to be put in place to manage environmental hazards and protect the environment and must include the following information:
- (a) a description of how the environmental protection plan ensures that the obligations set out in these Regulations with regard to environmental protection are met;
- (b) a summary of the studies and a description of the processes used to
- (i) identify the environmental hazards that may arise during the authorized work or activities, including any environmental hazards that may arise due to activities taking place in the vicinity of the operations site, and
- (ii) assess the environmental risks associated with the identified hazards;
- (c) a description of the hazards identified under subparagraph (b)(i) and the results of the risk assessment under subparagraph (b)(ii);
- (d) the measures to be taken to anticipate, monitor, avoid and minimize the environmental risks associated with the identified hazards;
- (e) an evaluation of the anticipated effectiveness of the measures referred to in paragraph (d);
- (f) a description of the methods to be used to communicate with persons who may be directly affected by the identified hazards regarding the existence of those hazards and the measures that will be taken to minimize the associated environmental risks;
- (g) a description of all the facilities, equipment and systems that are critical to the protection of the environment and are to be used during the authorized work or activities and a summary of the procedures and policies to be put in place for their inspection, testing and maintenance;
- (h) a description of the organizational structure and the chain of command for ensuring that the authorized work or activities are carried on in a manner that minimizes environmental hazards;
- (i) a description of the procedure to be followed if an archaeological site or a burial ground is discovered during the authorized work or activities;
- (j) a description of the measures to be taken to monitor compliance with the environmental protection plan and to evaluate performance in relation to the plan’s objectives, including data collection and analysis, inspections and auditing; and
- (k) a description of the processes to be put in place to identify, evaluate and manage any changes related to the authorized work or activities that could affect the protection of the environment.
Service providers
(2) If the operator contracts for the provision of services with respect to the authorized work or activities, the environmental protection plan must also include
- (a) a description of how the procurement process takes into consideration service providers’ past performance in relation to environmental protection;
- (b) a description of service providers’ roles and responsibilities with respect to environmental protection;
- (c) a description of the measures to be taken to oversee the work or activities of service providers and to ensure that service providers comply with the environmental protection plan; and
- (d) a description of how the operator and service providers will communicate with each other regarding any environmental issues that may arise during the work or activities.
Emergency management plan
54 (1) The emergency management plan must set out the emergency response procedures referred to in subsection (2) and any other procedures, practices and resources that are necessary to effectively prepare for, manage and respond to an emergency and must include the following information:
- (a) a description of how the emergency management plan ensures that the obligations set out in these Regulations with regard to emergency response are met;
- (b) a description of the types of incidents, in relation to the authorized work or activities, that may require an emergency response, an assessment of the risks associated with each type of incident and a description of the planned emergency response for each type of incident;
- (c) a description of the organizational structure and the chain of command for emergency response;
- (d) a method for classifying incidents;
- (e) a description of the incident management system to be used for emergency response;
- (f) a description of the methods to be used to monitor, constantly and in real time, both the facilities used in the generation and transmission of electrical energy and the work or activities, including at night and during periods of poor visibility;
- (g) the frequency and scope of the emergency response drills and exercises to be carried out to test and validate emergency response procedures and practices; and
- (h) a description of the measures to be taken to ensure that first responders, the personnel of relevant medical facilities, organizations and agencies, and persons that are carrying on activities within or in the vicinity of an operations site are informed of, and provided with instructions and updates concerning,
- (i) the location of the facilities that are to be used in the generation and transmission of electrical energy,
- (ii) the potential emergency situations that may arise in relation to those facilities, and
- (iii) the procedures to be followed in case of an emergency.
Emergency response procedures
(2) The emergency response procedures must cover the following subjects:
- (a) emergency response for each type of incident identified under paragraph (1)(b), including the emergency equipment that is necessary and is to be made available for emergency response to each type of incident;
- (b) the safe shutdown, in the event of an emergency, of facilities, equipment and systems to be used in the generation and transmission of electrical energy;
- (c) evacuation plans for personnel carrying on work or activities in the offshore area, including, if applicable, evacuation plans for divers engaged in a dive;
- (d) the notification, investigation and reporting of incidents under section 64;
- (e) the protocols for communicating with the relevant federal, provincial and municipal authorities and Indigenous governing bodies during an emergency response; and
- (f) coordination and liaison with all relevant emergency response organizations during an emergency response.
Implementation of Plans and Other Requirements
Implementation
55 (1) The operator must ensure that there are sufficient financial and human resources to implement and continually improve the safety plan, environmental protection plan and emergency management plan.
Accountable person
(2) The operator must designate one of its employees as the accountable person for the safety plan, environmental protection plan and emergency management plan and ensure that the accountable person has the necessary authority for assigning financial and human resources to develop, implement and make ongoing improvements to those plans.
Change — accountable person
(3) If there is any change to the name, position or contact information of the accountable person that was submitted under paragraph 51(2)(a), the operator must provide updated information to the Regulator as soon as feasible.
Conduct of authorized work or activities
56 (1) The operator must carry on all authorized work or activities in a manner that ensures safety, security and environmental protection by
- (a) meeting the requirements of the safety plan, environmental protection plan and emergency management plan and ensuring that all employees, suppliers, service providers and other persons involved in the authorized work or activities meet those requirements;
- (b) monitoring the compliance of employees, suppliers, service providers and other persons involved in the authorized work or activities with all conditions of authorization;
- (c) ensuring the safe and reliable operation of facilities, equipment and systems related to the offshore renewable energy project or offshore power line;
- (d) taking all reasonable measures to minimize damage to property;
- (e) taking all reasonable measures to minimize adverse effects for other persons in the offshore area;
- (f) using the best available technologies for mitigating adverse effects on persons and the environment that are economically feasible to implement;
- (g) complying with prevailing industry standards and best practices;
- (h) taking all reasonable measures to prevent debris and to prevent or, if prevention is not possible, minimize the introduction into the environment of any substance or form of energy that is likely to have an adverse effect on the environment; and
- (i) taking all reasonable measures to minimize any adverse effects on persons and the environment when restoring the operations site after the decommissioning and abandonment of the facilities, equipment and systems.
Equipment and systems
(2) The operator must ensure that
- (a) all equipment and systems that are used during the authorized work or activities are tested, inspected, maintained, operated and handled in such a way as to ensure safety, security and environmental protection, taking into consideration the manufacturer’s instructions and any applicable standards; and
- (b) any defective components of the equipment or systems are promptly repaired or replaced, taking into consideration the manufacturer’s instructions and any applicable standards.
Assignment of duties
(3) The operator must ensure that persons who are assigned duties or who carry out authorized work or activities
- (a) have the necessary experience, training, qualifications and competence to perform the duties or carry on the work or activities in accordance with these Regulations and in a manner that ensures safety, security and environmental protection; and
- (b) are sufficient in number and receive the supervision that is necessary for them to perform the duties or carry on the work or activities in a manner that ensures safety, security and environmental protection.
Navigational safety zones
57 (1) The operator must take measures to protect facilities, equipment and systems at an operations site against collision with vessels, vehicles, aircraft and other conveyances operating in the vicinity of the facilities, equipment and systems from the time their construction begins until their decommissioning and abandonment is completed, including by
- (a) establishing the navigational safety zones referred to in paragraph 51(2)(e) that are approved by the Regulator; and
- (b) ensuring that the following information is made available to other persons in the offshore area and brought to the attention of the Canadian Coast Guard, the Department of Transport and the Canadian Hydrographic Service of the Department of Fisheries and Oceans:
- (i) the location of the operations site and of the facilities, equipment and systems,
- (ii) the boundaries of the navigational safety zones, and
- (iii) a description of the risks associated with navigation in the vicinity of the facilities, equipment and systems.
Boundaries of navigational safety zone
(2) The establishment of the boundaries of a navigational safety zone must be informed by the risk assessment referred to in paragraph 50(l) as it relates to the risks associated with navigation in the vicinity of the facilities, equipment or systems at the operations site, but the distance between the outer extremity of the facilities, equipment or systems and the perimeter of the safety zone must not exceed 500 m in any direction, except as permitted under paragraph 5 of Article 60 of Part V of the United Nations Convention on the Law of the Sea.
Routing systems and measures
(3) A navigational safety zone must not interfere with the use of established routing systems and routing measures related to navigational safety.
Design requirements
58 (1) The operator must ensure that all facilities, equipment and systems related to the offshore renewable energy project or offshore power line are designed
- (a) in such a way as to ensure safety, security and environmental protection;
- (b) using the best available technologies for minimizing adverse effects on persons, infrastructure and the environment that are economically feasible to implement; and
- (c) in accordance with prevailing industry standards and best practices.
Factors to be taken into account
(2) The design of the facilities, equipment and systems must take into account their intended use, their location and any site-specific physical and environmental conditions.
Physical and environmental conditions
(3) The operator must ensure that every facility related to the offshore renewable energy project or offshore power line is designed to withstand or avoid all reasonably foreseeable site-specific physical and environmental conditions, including any reasonably foreseeable combination of those conditions, without its structural integrity or any associated equipment or systems that are critical to safety, security and environmental protection being compromised.
Rescue boat
59 The operator must ensure that a rescue boat is available and ready for use in the event of an emergency at all times when personnel are present in the offshore area for the purposes of carrying on authorized work or activities.
Requirements for vessels
60 The operator must ensure that every vessel that is used to carry on authorized work or activities is suitable for the operations site at which it is used and for the nature of the work or activities.
Evacuation systems and equipment
61 In determining the number of persons that any lifeboat, life raft or marine evacuation system can accommodate, the operator must take into consideration each person’s weight while the person is wearing an immersion suit, as well as the space they require while wearing such a suit.
Access to documents and information
62 The operator must ensure that a copy of the following documents and information is readily accessible at each operations site when personnel are present and at all times at every associated control centre and emergency response operations centre:
- (a) every authorization issued in respect of work or activities related to the offshore renewable energy project or offshore power line;
- (b) all information and documents submitted to the Regulator to meet a condition of authorization, including the safety plan, environmental protection plan and emergency management plan, as well as supporting documentation; and
- (c) all procedures and other documents that are necessary to carry on authorized work or activities in a manner that ensures safety, security and environmental protection.
PART 3
Notification, Investigation, Reporting and Record-Keeping Requirements for Operators
Application
63 This Part applies in respect of all offshore renewable energy projects and offshore power lines.
Notification of incidents
64 (1) The operator must notify the Regulator of any reportable incident as soon as the circumstances permit after the incident occurs.
Investigation
(2) The operator must ensure that every reportable incident is investigated.
Incident report
(3) The operator must, within 14 days after the day on which a reportable incident occurs, submit a report to the Regulator that includes the following information:
- (a) a description of the reportable incident, where and when it occurred and who was involved;
- (b) a description of the impact of the reportable incident on the facilities, equipment and systems related to the offshore renewable energy project or offshore power line, as well as on vessels, persons and the environment;
- (c) the results of the investigation into the reportable incident, including details regarding the root cause of the reportable incident and causal and contributing factors;
- (d) a description of any repairs undertaken to restore any damaged structures to their original design strength or to restore the functionality of any impacted equipment or systems;
- (e) a description of the measures put in place to prevent the occurrence of similar reportable incidents;
- (f) if emergency response procedures were implemented, a description of
- (i) any communications that occurred with the relevant federal, provincial and municipal authorities and Indigenous governing bodies, and
- (ii) any coordination and liaison with relevant emergency response organizations; and
- (g) any other relevant information.
Periodic reports
65 (1) The operator must submit periodic reports to the Regulator summarizing the following in respect of the period that has elapsed since the day on which the authorization was issued in respect of the work or activities in question or the day after the last day included in the preceding periodic report, as the case may be:
- (a) the work or activities performed;
- (b) the status of the offshore renewable energy project or offshore power line, by reference to the execution plan referred to in paragraph 6(e) or 50(e), as the case may be;
- (c) any deviations from or changes to the execution plan;
- (d) any emergency response drills or exercises referred to in paragraph 11(1)(g) or 54(1)(g), as the case may be, that were carried out;
- (e) any instances of non-conformity with these Regulations and the corrective actions taken; and
- (f) any reportable incidents and any situations that had the potential to result in a reportable incident.
Beginning of commercial production
(2) The periodic reports must also set out the planned date for the beginning of commercial production of renewable energy, if applicable.
Frequency of submission
(3) The periodic reports must be submitted at the following frequency unless the Commission requires them to be submitted more frequently as a condition of authorization:
- (a) in the case of an offshore renewable energy project or offshore power line to which Part 1 applies,
- (i) monthly, in respect of authorized work or activities in relation to the construction or the decommissioning and abandonment of facilities, equipment and systems related to the project or power line, and
- (ii) annually, in respect of authorized work or activities in relation to site assessment or the operation and maintenance of facilities, equipment and systems relate to the project or power line; and
- (b) in the case of an offshore renewable energy project or offshore power line to which Part 2 applies, annually.
Final report
66 The operator must, within six months after the day on which all authorized work or activities related to the offshore renewable energy project or offshore power line are completed, submit to the Regulator a final report that includes the following information:
- (a) a statement as to whether the work or activities were carried on as planned and as authorized;
- (b) if the work or activities were not carried on as planned and as authorized, a description of the manner in which the carrying on of the work or activities deviated from what was planned and authorized; and
- (c) a description of the state of the operations site as of the completion of all authorized work and activities.
Record keeping
67 (1) The operator must keep, at the operator’s principal place of business in Canada, electronic records of
- (a) any documents and information submitted to the Regulator in support of an application for authorization;
- (b) the results of the surveys and programs referred to in subparagraph 6(f)(i) or 50(f)(i), as the case may be, and, if applicable, the surveys referred to in paragraph 12(a);
- (c) all documents and information submitted to the Regulator to meet a condition of an authorization; and
- (d) all documents and information that demonstrate that the authorized work or activities were carried on
- (i) in a manner that is in keeping with any information provided and any approach, methodology or technology proposed in an application in respect of the authorized work or activities, and
- (ii) in conformity with these Regulations.
Disclosure of records
(2) The operator must, on request, disclose the records to the Regulator in the form and manner specified by the Regulator.
Duration of retention
(3) The records must be retained for five years after the day on which the decommissioning and abandonment of the facilities, equipment and systems related to the offshore renewable energy project or offshore power line ends, or, if the project or power line is terminated before any construction takes place, for five years after the day on which the site assessment ends.
PART 4
Coming into Force
Registration
68 These Regulations come into force on the day on which they are registered.
REGULATORY IMPACT ANALYSIS STATEMENT
(This statement is not part of the Regulations.)
Executive summary
Issues: The Canadian Energy Regulator Act (CER Act) came into force in 2019 setting out the legislative framework for the oversight of the full life cycle of an offshore renewable energy (ORE) project and offshore power line. The CER Act specifies what factors must be considered by the Commission in determining whether to issue an authorization to carry out any work or activity related to an ORE project or offshore power line, but it does not provide the detailed requirements that must be met by an operator in order to obtain the authorization, conditions that may be imposed on an authorization, or the requirements that must be continually met to ensure that those works or activities can be executed in a manner that protects the environment and the safety and security of persons and infrastructure.
Description: The Canada Offshore Renewable Energy Regulations (the “Regulations”) operationalize Part 5 of the CER Act by establishing comprehensive requirements respecting work and activities related to ORE projects and offshore power lines for the purposes of safety, security, and environmental protection.
Rationale: Regulations are required to operationalize the ORE regime under the CER Act and to provide the certainty needed for the ORE industry to develop in Canada. The Regulations would contribute to ensuring the safety, security, and environmental protection of ORE projects in Canada. The net impact of the Regulations was considered qualitatively, with incremental benefits including improved safety, security, and environmental outcomes for ORE projects. Incremental costs arising from the Regulations would average less than $1 million yearly and stem from the labour costs associated with mandatory reporting and inspection requirements for all ORE projects, as well as costs related to the involvement of a certifying authority at the operations phase of a wind energy project.
Issues
Part 5 of the CER Act provides the legislative framework for oversight of the full life cycle of an offshore renewable energy (ORE) project and offshore power line. The CER Act provides the authority for the Commission of the Canada Energy Regulator (CER or Regulator) to issue authorizations for any work or activity related to those projects or power lines. The CER Act specifies the factors that must be considered in determining whether to issue an authorization, but it does not provide the detailed planning and technical requirements that must be met by an operator in order to obtain the authorization, the conditions that may be imposed on the authorization, or the requirements that must be continually met to ensure that those works and activities can be executed in a manner that ensures safety, security, and environmental protection.
The Regulations are required to operationalize the ORE regime under the CER Act and to provide the certainty needed for the ORE industry to develop in Canada’s federally regulated offshore areas.
Background
Over 70% of the earth’s surface is covered by seas and oceans that contain vast energy potential that can now be harnessed through advances in ORE technologies. ORE refers to electricity that is generated from ocean-based resources, such as offshore wind, waves, tides, currents and solar.
As the world looks for cleaner sources of power, ORE is gaining prominence, with offshore wind taking the lead and accounting for most commercial ORE developments while other technologies, such as wave and tidal, continue to work through the research and demonstration stages of technology development. Globally, the offshore wind industry has grown rapidly with more than 72 000 megawatts of installed capacity in 2023, representing a more than twentyfold increase in the amount of energy produced worldwide from offshore wind since 2010. According to the International Energy Agency, global offshore wind capacity may increase fifteenfold from 2019 and attract around $1 trillion of cumulative investment by 2040.
Offshore wind energy has become increasingly competitive as costs associated with the industry begin to rapidly decline. Many international jurisdictions have set ambitious offshore wind energy targets to help meet their climate goals and electrify new industries, such as clean hydrogen production. Because offshore wind facilities are capable of producing renewable energy at scales significantly greater than those of onshore wind and solar, it opens the opportunity to scale up the production of clean hydrogen and other energy conversion technologies, which could aid in the decarbonization of the transportation and hard-to-abate energy-intensive sectors.
Canada’s vast coastlines represent significant ORE resources and untapped potential for a low-carbon economic opportunity, which could make an important contribution to Canada’s goal of net-zero emissions by 2050, the electrification and decarbonization of Canada’s economy and the advancement of Canada’s clean hydrogen industry and exports while stimulating economic opportunities for coastal provinces, territories, and communities.
On August 28, 2019, the CER Act came into force and repealed the National Energy Board Act. The CER Act created the CER, which replaced the former National Energy Board. Part 5 of the CER Act established the legislative framework for offshore renewable energy projects and offshore power lines, creating the authority to regulate the work and activities related to the full life cycle of ORE projects and offshore power lines located in the federal offshore area (which is commonly defined in maritime law as the waters falling seaward of the low water mark, excluding provincial waters located within the jaws of the land, and extending to the outer limits of the exclusive economic zone), from initial site assessment work to identify areas with potential to support ORE projects, to the eventual decommissioning and abandonment of project.
Part 5 of the CER Act also provides the authority to make regulations respecting safety, security, and environmental protection of ORE projects, to ensure industry and other stakeholders have a clear understanding of expectations regarding safety, security, and environmental protection, and to ensure ORE project proponents adopt best practices and best available technologies throughout the life cycle of projects.
Following the CER Act entering into force, Natural Resources Canada (NRCan) established the Offshore Renewable Energy Regulations Initiative (ORER Initiative) to develop the regulatory framework that would operationalize Part 5 of the CER Act and ensure that the highest level of safety, security, and environmental protection is achieved throughout the life cycle of ORE projects. The CER, as the life cycle regulator responsible for enforcing these Regulations, provided technical support and expertise to the ORER Initiative.
NRCan undertook extensive engagement on the ORER Initiative, starting in fall 2020 on the conceptual approach to the Regulations through to the proposed regulations that were pre-published in the Canada Gazette, Part I, in February 2024. Throughout the regulatory development process, more than 200 parties were engaged, including renewable energy industry companies/developers, industry associations, Indigenous groups and governments, certifying authorities, interested provinces and territories (notably the governments of Nova Scotia and Newfoundland and Labrador), regulators, fishing groups, and environmental non-governmental organizations.
The ORER Initiative proposed a combination approach of management-based and outcome-based regulatory frameworks, with a strong emphasis on safety management systems and planning, that would require operators to proactively anticipate, manage, mitigate and, where possible, eliminate potential hazards to safety, security, and the environment through various management, planning, and analysis activities. This combination approach provides the flexibility necessary to support the use of innovations in science, technologies, and methodologies that would increase safety, security, and environmental protection while reducing costs and allowing the Regulations to remain evergreen as the ORE sector evolves over time.
On October 3, 2024, Bill C-49 received Royal Assent; the Bill proposed amendments to the Canada-Nova Scotia Offshore Petroleum Resources Accord Implementation Act and the Canada–Newfoundland and Labrador Atlantic Accord Implementation Act (collectively referred to as the “Accord Acts”) to expand the existing offshore joint-management framework to enable new clean energy opportunities for the region and to expand the mandates of the Canada-Nova Scotia Offshore Petroleum Board and the Canada–Newfoundland and Labrador Offshore Petroleum Board to include the regulation of ORE in the respective joint-management areas. Once the legislation is in force, the CER Act will no longer apply in the Canada–Nova Scotia and Canada-Newfoundland and Labrador joint-management areas. Regulations respecting the safety, security, and environmental protection of ORE projects in those areas are required to operationalize the amended legislation. These Regulations will form the basis of the future proposed Regulations under the amended Accord Acts.
Objective
The primary objective of these Regulations is to provide a comprehensive regulatory regime to guide the work and activities related to ORE projects and offshore power lines in Canada’s federal offshore areas. The Regulations are designed to ensure that work and activities related to ORE projects and offshore power lines are undertaken in a manner that meets the prevailing industry standards and best practices for safety, security, and environmental protection.
The Regulations will also provide the certainty needed to inform development and investment decisions in Canada’s federal offshore area.
Description
The CER Act prohibits any work or activity that is related to an ORE project to be carried out in the offshore area, except in accordance with an authorization issued by the Commission of the CER. The Act defines an ORE project as including any research or assessment conducted in relation to the exploitation or potential exploitation of a renewable resource to produce energy, any exploitation of a renewable resource to produce energy, and the storage or transmission of such energy. In addition, the Act also requires that any work or activity related to the construction, operation, or abandonment of any part of an offshore power line that is in a province be authorized by the Commission.
Accordingly, the Regulations set out the requirements of an application for the authorization to carry out any work or activities related to an ORE project or offshore power line, the conditions of the authorization that must be met by an operator before the authorized work or activities can commence, and the ongoing requirements that an operator must meet while carrying out the authorized work or activity.
Given that ORE technologies are at different stages of technological readiness, the Regulations have been divided into three parts: the first part addresses the requirements for offshore wind energy projects and associated offshore power lines, where the technologies have reached large-scale global commercial development; the second part addresses the requirements for ORE projects and associated power lines other than offshore wind energy, where technologies remain primarily in the research and demonstration phase of technological development and are not expected to reach large-scale size or complexity in the near-future; and the third part addresses requirements related to reporting and record-keeping which apply to all types of ORE projects.
The regulatory requirements have been designed to be right sized for the scale and associated risk of the various types of ORE projects that may reasonably be expected in the coming decade. Part I provides a comprehensive framework for offshore wind projects, while Part II provides a regulatory framework for non-wind ORE projects. This approach for non-wind ORE is intended to ensure that the regulatory regime does not stifle development and use of new technologies.
PART I — Wind energy
Applications for authorizations
Part I sets out the requirements that an operator of an offshore wind energy project must meet in order to obtain an authorization for the suite of work or activities they propose to carry out at each major phase of a wind energy project’s life cycle — site assessment, construction and operations, and decommissioning and abandonment. This approach allows for one application and related authorization for each major phase of a wind energy project, rather than having numerous individual applications and authorizations for each discrete work or activity at each phase.
Every application
Every application related to a wind energy project, regardless of the phase of the project, would contain a minimum set of requirements, as well as phase-specific requirements, which are tailored to the nature of work and risk level associated with the respective phase.
The level of detail required in the application, as well as any documents and information submitted, must be commensurate with the scope, nature, and complexity of the proposed work or activities. For example, during the site assessment phase of a wind energy project, risks are much lower than in the construction or decommissioning and abandonment phases. The Regulations appropriately consider and reflect this difference.
Every application requires detailed information regarding the proposed work and activities. This includes
- Contact information of the operator’s authorized representative.
- An overview of the development concept for the project, including any plans to execute the project in phases.
- A description of the work the operator wants to do at the phase of the life cycle to which the application would apply, including the objectives, scope, and location of the proposed work and a plan and schedule for carrying out the work.
- Information about any anticipated vessels, aircraft, vehicles, and equipment the operator expects to use.
- Results of past relevant surveys and monitoring programs related to the project, and how these results influence the current plans.
- A description of the measures that the operator proposes to use to ensure compliance with all applicable safety, security, and environmental laws.
- A description of the potential effects that the work or activities that are the subject of the application may have on any other users of the operations site.
- A list of all necessary permits and other authorizations that are required in relation to the proposed work or activities.
- The target safety, security, and environmental protection levels for the proposed work or activities, which describe qualitatively or quantitatively (if possible) the measurable objectives for safety, security, and environmental protection that the operator commits to achieving while carrying on the proposed work or activities.
- In the case where the operator is proposing to carryout work or activities in a manner that differs from what was proposed in an earlier application for authorization, a description of the changes that are being proposed and the rationale and effects of those proposed changes.
Additional application requirements — Site assessment
In addition to the requirements of every application for authorization related to a wind energy project, applications to undertake work or activities related to the site assessment phase of the project must also provide
- Details about the proposed surveys, analyses or assessments to be conducted.
- Information about any equipment that would be installed or used for the site assessment work or activities, and how that equipment would be abandoned or removed.
- A risk assessment that addresses the safety and security of persons and infrastructure involved in, or in the vicinity of, the site assessment work or activities.
- An environmental and socio-economic assessment of the site assessment work or activities.
- An assessment that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the CER Act, which include the interests and concerns of the Indigenous peoples of Canada and any effects on the rights of the Indigenous peoples of Canada recognized and affirmed by section 35 of the Constitution Act, 1982.
Additional application requirements — Construction and operations
In advance of the construction and operations phase of a wind energy project, details related to the full life of the project, up to and including high-level plans for the eventual decommissioning and abandonment of project infrastructure, is required.
In addition to the requirements of every application for authorization, applications to undertake work or activities related to the construction and operations phase of a wind energy project must include project details related to the full life cycle of the project, notably the following:
- A list of the industry standards and best practices the operator proposes to follow in designing the project, along with data sets for operational and extreme conditions.
- A description of the proposed facilities, equipment, and systems for the project, including their location, capabilities, and limitations.
- A description of any existing infrastructure in the area, and how it was considered during planning.
- A risk assessment of the proposed work or activities for the construction, operation, and maintenance of the wind energy project as well as the anticipated work or activities for its decommissioning and abandonment, that addresses the safety and security of persons and infrastructure involved in, or in the vicinity of, the work or activities related to the construction and operations of the project.
- An environmental and socio-economic assessment for the work or activities related to the construction and operations of the wind energy project.
- An assessment that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the CER Act, which include the interests and concerns of the Indigenous peoples of Canada and any effects on the rights of the Indigenous peoples of Canada recognized and affirmed by section 35 of the Constitution Act, 1982.
- A description of the quality assurance program, including the standard to which the program conforms, required under the Regulations for the monitoring, documenting, and managing of quality during the fabrication, transportation, installation, and commissioning of project facilities, equipment, and systems.
- The name of the organization proposed to be used as the project’s certifying authority, their qualifications, and the proposed general scope and timing of the activities they will perform. The roles and responsibilities of the certifying authority are discussed further below.
- An overview of the anticipated plan for decommissioning and abandonment of the project, including the forecasted costs and how the operator plans to finance or pay for them.
The technical details required in the application for authorization at the construction and operations phase are expected to reflect the range of design parameters within which the project would be designed, while the final design details must be submitted to the Regulator as part of the conditions of authorization, ahead of any authorized work or activity commencing, as discussed further in this analysis. This approach, known as a “project envelope approach,” has been used successfully in the United States and Europe and provides flexibility for an operator to use the latest technologies and methodologies by not having to lock in the design too early in the project approval process, thereby minimizing the need for additional technical reviews, should design or technologies change during the approval process. A key element of the regulatory framework for offshore wind energy is the requirement that the operator engage the services of a certifying authority to serve as an independent, third-party assessment and verification body. Specifically, the certifying authority, which must be approved by the Regulator, would be involved in the project’s facilities, equipment, and systems from their design conception up to the end of operations.
The certifying authority must be selected by the operator, and approved by the Regulator, based on the organization’s qualifications to assume the responsibilities as outlined in the Regulations, including but not limited to
- Confirming that the proposed design, fabrication, construction, and installation of project facilities, equipment, and systems conform with good engineering practices, the authorization, and all applicable laws.
- Monitoring and inspecting the project development through fabrication, transportation, construction, installation, and commissioning.
- Issuing a certificate of fitness that confirms that the facilities, equipment, and systems are fit for the purposes for which they are to be used and can be operated without posing a threat to safety, security, or the environment.
- Performing inspections, in accordance with the inspection plan, of the facilities, equipment, and systems during the operations phase, and verifying the continued validity of the certificate of fitness.
The certifying authority will communicate directly with the Regulator and will be required to develop and submit to the Regulator for approval, a scope of work for executing these responsibilities, prior to commencing any of the activities contemplated in the scope of work.
The certifying authority must also develop and submit to the Regulator an inspection plan for the periodic inspections of facilities, equipment, and systems during construction and operations of the project, and must include a schedule for the periodic review of the operator’s records from the management system to identify any changes that might affect safety, security, or environmental protection. The scope and frequency of inspections must be determined in accordance with prevailing industry standards and best practices and may involve either on-site or remote inspections.
For each calendar year, the certifying authority must also submit a report to the Regulator in relation to its oversight of any construction, operation and maintenance work or activities that were carried out by the operator during that calendar year.
Throughout the undertaking of its responsibilities, the certifying authority must monitor for real, potential, or perceived conflicts of interest and flag these with the Regulator without delay should they occur.
Additional application requirements — Decommissioning and abandonment
A project’s facilities, equipment, and systems must be abandoned in accordance with an authorization; otherwise, they are considered debris under the CER Act and the operator is financially liable. In addition to the requirements of every application for authorization, applications to undertake work or activities related to decommissioning and abandonment of an offshore wind project must also provide
- Information about any existing infrastructure in the area, and how it was considered during planning.
- The results of an assessment of the condition of any facilities, equipment, or systems that will be decommissioned and abandoned, and details on the proposed approach to decommissioning and whether they will be left in place or removed and disposed of. If removal is planned, the details on the proposed methods for removal, transportation, and disposal must be provided.
- A description of the methods that will be used to restore the site after decommissioning and abandonment, ensuring it returns to its original state.
- An updated forecast of the costs associated with decommissioning and abandonment, along with details on how the operator plans to finance or pay for them.
- A risk assessment that addresses the safety and security of persons and infrastructure involved in, or in the vicinity of, the work or activities related to decommissioning and abandonment of the wind energy project, including any risks associated with the navigation of vessels, vehicles, aircraft, or other conveyances in the vicinity.
- An environmental and socio-economic assessment of the work or activities related to the decommissioning and abandonment of the wind energy project.
- An assessment that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the CER Act, which include the interests and concerns of the Indigenous peoples of Canada and any effects on the rights of the Indigenous peoples of Canada recognized and affirmed by section 35 of the Constitution Act, 1982.
Conditions of every authorization
The CER Act sets out that an authorization is subject to any conditions that may be imposed by the Commission or under the Regulations. The Regulations prescribe four main conditions that apply to every authorization, as well as conditions that relate to specific phases, of the offshore wind energy project lifecycle. An operator cannot commence the authorized work or activities until all conditions have been satisfied and accepted by the Regulator. This approach allows the operator the opportunity to obtain early approval of the general planned approach for how they will conduct the proposed work or activities related to the wind energy project while it finalizes the detailed planning requirements and technical specifications associated with the authorized work or activities.
Management system
The Regulations require the operator of a wind energy project to establish and implement a proactive and comprehensive management system for the management and coordination of the authorized work. The management system must establish the overarching direction and framework for reducing risks to safety, security, and the environment, including measures for ensuring the reliable operation of the facilities, equipment, and systems related to a wind energy project and any associated offshore power line, and to ensure appropriate response in the event of an emergency.
The management system must demonstrate the operator’s commitment to continuous improvement through the setting and achieving of measurable goals and performance indicators related to safety, security, and environmental protection. The management system must include policies, procedures, and practices to guide the planning and execution of work; processes for continuous hazard identification; processes for risk assessment and determination of appropriate corrective and preventative measures; and processes for audit and evaluation of the management system to determine whether goals and performance indicators are met. The management system must also include processes for effectively coordinating and managing the work undertaken by different parties involved in the project, as well as processes for internal and external communication regarding safety, security, environmental protection, reliability, and emergency response.
Safety plan
The safety plan builds upon the preliminary risk assessment that was submitted as part of the application for authorization and is a comprehensive document intended to guide the safe execution of work. The safety plan must set out the procedures, practices, resources, and the sequence of key safety-related activities necessary to safely carry out the authorized work or activities and includes, among other things, the following information:
- A description of how the safety plan will integrate the relevant elements of the management system.
- Identification of the organizational structure and chain of command for ensuring the work is carried out safely.
- A summary of the studies the operator has undertaken to identify and assess the safety hazards and risks associated with the specific authorized work or activities.
- A description of the safety hazards and risks that were identified, and the measures that will be taken by the operator to anticipate, monitor, avoid, and minimize those hazards and risks.
- The methods for communicating with people directly affected by those hazards, informing them about the risks and mitigation measures.
- A description of the facilities, equipment, and systems that are critical to safety and a summary of the procedures and policies that will be put in place for their inspection, testing, and maintenance.
- A detailed description of the support craft and other vessels, vehicles, aircraft or conveyances that will be used.
- A description of any planned diving operations, including the measures that will be taken to ensure that those operations are carried out safely and in accordance with the prevailing industry standards and best practices that are appropriate for the water depth and type of diving to be carried out.
- The measures that will be taken for detecting, forecasting, surveilling, and reporting any ice or icing hazards that may exist, as well as measures for data collection and, if applicable, for ice avoidance or deflection.
- The training needed for those doing the work, including their required experience, qualifications, and competencies.
- How the operator will monitor compliance with the safety plan, including work subcontracted to other service providers, through data collection, inspections, and audits, and how the operator intends to manage any changes in the work or activities that may affect safety.
Environmental protection plan
The environmental protection plan builds upon the preliminary environmental assessment that was submitted as part of the application for authorization and is a comprehensive document intended to ensure the operator will protect the environment while undertaking the authorized work or activities. The environmental protection plan must set out the procedures, practices, and resources that will be put in place to manage environmental hazards and protect the environment and must include, among other things, the following information:
- A description of how the environmental protection plan will integrate the relevant elements of the management system.
- Identification of the organizational structure and chain of command for ensuring the work is carried out in a manner that minimizes environmental hazards.
- A summary of the studies the operator has undertaken to identify and assess the environmental hazards and risks associated with the specific authorized work or activities.
- A description of the environmental hazards and risks that were identified, and the measures that will be taken by the operator to anticipate, monitor, avoid, and minimize those hazards and risks.
- The methods for communicating with people directly affected by those hazards, informing them about the risks and mitigation measures.
- The procedures that will be followed if an archaeological site or a burial ground is discovered during the authorized work or activities.
- A description of the facilities, equipment, and systems that are critical to the protection of the environment and summarize the procedures and policies that will be put in place for their inspection, testing, and maintenance.
- How the operator will monitor compliance with the environmental protection plan, including work subcontracted to other service providers, through data collection, inspections, and audits, and how the operator intends to manage any changes in the work or activities that may affect the protection of the environment.
Emergency response plan
The emergency response plan must set out the operator’s processes, procedures, and resources for preparing for, managing, and responding to any emergency that may arise while executing the authorized work or activities.
The operator must identify, through a hazard identification and risk assessment process, the potential incidents that may arise that would require an emergency response. The plan describes the organizational structure and chain of command for emergency response, provides a method for classifying incidents, and outlines the incident management system. It is also required to provide details on any real-time monitoring of facilities and operations that the operator intends to use, details on the drills and exercises that would be undertaken for testing procedures, and the measures to be used to inform and instruct first responders, medical facilities, organizations, and users about facility locations, potential emergencies, and safety procedures.
Additional conditions — Construction and operations
In addition to the conditions of every authorization, the following documents and information, subject to detailed requirements outlined in the Regulations, must be submitted to and approved by the Regulator before any authorized work or activities related to construction of a wind energy project commences:
- A facility design report that provides comprehensive technical details regarding the design of the wind energy project’s facilities, equipment, and systems.
- A fabrication and construction report that provides comprehensive technical details of how those facilities, equipment, and systems would be fabricated, transported, constructed, and installed.
- A facility reliability report that outlines the measures that would be put in place to ensure the reliability of the power system and the impacts of the project on the bulk power system.
- A preliminary version of the integrity management plan that is required under the Regulations that, once finalized, would address the testing, inspection, monitoring, and maintenance of the wind energy project’s facilities, equipment, and systems.
- The certifying authority’s plan for the periodic inspection of facilities, equipment, and systems during the construction phase.
- A description of the proposed navigational safety zones to protect project infrastructure against collision by vessels and aircraft, or a justification as to why navigational safety zones are not needed.
In addition to the conditions of every authorization, the following documents and information must be submitted to and approved by the Regulator before any authorized work or activities related to operations of a wind energy project commences:
- The finalized integrity management program that meets the detailed specifications outlined in the Regulations.
- A preliminary version of the decommissioning and abandonment plan that provides an update to, and builds upon, the early overview of the plan and forecasted costs that were previously provided at the application stage.
- The certifying authority’s plan for the periodic inspection of facilities, equipment, and systems during the operations phase.
- The certificate of fitness, issued by the certifying authority, confirming that the project’s facilities, equipment, and systems are fit for the purposes for which they are to be used and can be operated without posing a threat to safety, security, or the environment.
- A description of the proposed navigational safety zones to protect project infrastructure against collision by vessels and aircraft, or a justification as to why navigational safety zones are not needed.
Additional conditions — Decommissioning and abandonment
In addition to the conditions of every authorization, the following documents and information must be submitted to and approved by the Regulator before any authorized work or activities related to the decommissioning and abandonment of a wind energy project commences:
- A finalized decommissioning and abandonment plan, as set out in the Regulations, detailing the proposed approach for the work to be executed, the safety and environmental protection measures to be implemented during these activities to ensure compliance with all applicable laws, a description of the potential effects that the work would have on the environment and on any other users of the operations site, and the methods that would be used to restore the operations site after the decommissioning and abandonment.
- A description of the proposed navigational safety zones to protect project infrastructure against collision by vessels and aircraft, or a justification as to why navigational safety zones are not needed.
Ongoing requirements for operators
Conduct of authorized work or activities
The Regulations require the operator to ensure that the authorized work or activities related to a wind energy project are carried out in a manner that protects safety, security, and the environment. Requirements include, but are not limited to
- Taking all reasonable measures to prevent debris and to minimize the introduction into the environment of any substance or form of energy that is likely to have an adverse impact on the environment, and to minimize damage to property and any adverse impacts on other users of the sea.
- Designating a person with the necessary authority to develop, implement and make ongoing improvements to the Management System and various plans.
- Ensuring ongoing compliance with the requirements of the management system, safety plan, environmental protection plan, emergency management plan, integrity management program, and quality assurance program, and making sure everyone involved in the project also complies with the requirements of those plans and programs.
- Ensuring there is adequate supervision of personnel and that they are competent and in sufficient numbers to ensure the work is executed in a manner that ensures safety, security, and environmental protection.
- Ensuring the safe and reliable operations of all project facilities, equipment, and systems, and ensuring that they are tested, inspected, maintained, operated, and handled to ensure safety, security, and environmental protection.
Design requirements
The Regulations require the operator to ensure that all infrastructure related to a project is designed to ensure safety, security, and environmental protection, taking into account their intended use, location, and associated site-specific physical and environmental conditions. The design must conform with prevailing industry standards and best practices and use the best available technologies for minimizing adverse effects on people, infrastructure, and the environment.
The operator must also design the project infrastructure to handle or avoid any reasonably foreseeable physical or environmental conditions at the specific site, including all possible combinations of these conditions. The design must ensure that the infrastructure, as well as its critical systems and equipment for safety, security, and environmental protection, remain intact and effective under these conditions.
Protection against collision and navigational safety zones
The Regulations require the operator to take measures to protect facilities, equipment, and systems at an operations site against collision with vessels, vehicles, aircraft and other conveyances operating in the vicinity of the project.
These measures could include the use of navigational safety zones, for which the operator would be required to determine, through a risk assessment, whether any such zones are necessary to protect project infrastructure against collision. The operator would need to propose any navigational safety zones to the Regulator, for its approval.
Consistent with Article 60 of the United Nations Convention on the Law of the Sea, the Regulations allow navigational safety zones of up to 500 m to be established around a facility, whether permanent or under construction, provided the safety zone does not interfere with any routing measures or systems that have been established for Canada. These routing measures and systems are typically established by either Transport Canada or the Canadian Coast Guard and are made available through the Canadian Coast Guard’s annual Notice to Mariners publication.
It is expected, however, that the maximum distance of 500 m may only be required during construction and decommissioning and abandonment activities, and that during steady state operations, the navigational safety zone may be reduced in size to minimize any impacts associated with reduced access to the operations site by other ocean users.
The operator would be required to ensure that the location of project facilities, any associated navigational safety zones, and any hazards that may exist in navigating within the vicinity of the facilities, is made available to other users of the ocean and brought to the attention of Transport Canada, the Canadian Coast Guard and the Canadian Hydrographic Service for potential inclusion in notices to mariners and/or nautical charts.
Vessels and offshore transportation considerations
In selecting any vessels to be used in the course of the authorized work or activities, the operator must ensure that vessels are suitable for the nature and location of the work or activity. In addition, in determining the number of persons that can be safely evacuated from a vessel, the operator must consider the additional space and weight considerations that arise from those evacuating personnel wearing marine abandonment/immersion suits.
The operator must ensure that a rescue boat is available and ready for use in the event of an emergency at all times when personnel are present in the offshore area for the purposes of carrying on the authorized work or activities.
If the operator intends to transport personnel to and from the offshore facilities by aircraft, the operator must ensure the aircraft landing area, or the area from where a person or cargo will be lowered or raised, is designed and maintained for safe landing and lifting/takeoff. The operator must develop procedures for the use of all equipment in the landing area, develop and provide a training program for personnel in the use of those procedures, and ensure that the aircraft service provider agrees to implement those procedures.
PART II — ORE other than wind energy
Part II sets out the requirements that an operator of an ORE project — other than a wind energy project — must meet to obtain an authorization for the individual or suite of work or activities it proposes to carry out related to the project. The requirements are similar to those required of an operator of a wind energy project, but adjusted to reflect the fact that these types of ORE projects are expected to be smaller in scale and less complex in nature. Should a proposed non-wind energy project be more complex in nature, the Regulator has the authority under the Act to require any additional information in the application it determines necessary, and the Commission has the authority under the Act to impose any additional conditions of authorization with respect to approvals that it considers necessary.
Applications for authorization
Every application related to a non-wind ORE project must provide detailed information regarding the proposed work and activities. Consistent with Part I, the level of detail required in the application, as well as any documents and information submitted, must be commensurate with the scope, nature, and complexity of the proposed work or activities. Every application must contain
- Contact information of the operator’s authorized representative, as well as the designated accountable person for the project.
- An overview of the development concept for the project, including any plans to execute the project in phases.
- A description of the work the operator wants to carry out under the authorization, including the objectives, scope, and location of the proposed work and a plan and schedule for carrying out the work.
- Information about any anticipated vessels, aircraft, vehicles, and equipment the operator expects to use.
- Results of past relevant surveys and monitoring programs related to the project, and how these results influence the current plans.
- A description of the measures that the operator proposes to use to ensure compliance with all applicable safety, security, and environmental laws.
- A description of the potential effects that the work or activities that are the subject of the application may have on any other users of the operations site.
- A list of all necessary permits and other authorizations that are required in relation to the proposed work or activities.
- A risk assessment that addresses the safety and security of persons and infrastructure involved in, or in the vicinity of, the work or activities, including any risks associated with the navigation of vessels, vehicles, aircraft, or other conveyances in the vicinity.
- An environmental and socio-economic assessment of the work or activities.
- An assessment that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the CER Act, which include the interests and concerns of the Indigenous peoples of Canada and any effects on the rights of the Indigenous peoples of Canada recognized and affirmed by section 35 of the Constitution Act, 1982.
- A list of the industry standards and best practices the operator proposes to follow in designing the project, along with data sets for operational and extreme conditions.
- A description of the proposed facilities, equipment, and systems for the project, including their location, capabilities, and limitations.
- An overview of the anticipated plan for decommissioning and abandonment of the project, including the forecasted costs and how the operator plans to finance or pay for them.
- In the case where the operator is proposing to carryout work or activities in a manner that differs from what was proposed in an earlier application for authorization, a description of the changes that are being proposed and the rationale and effects of those proposed changes.
Conditions of authorization
Part II of the Regulations sets out that a Safety Plan, Environmental Protection Plan, and Emergency Response Plan must be developed and implemented for the duration of the ORE projects. These plans must be approved by the Regulator ahead of the operator commencing any of the authorized work or activities. The required content of these plans under Part II is consistent with the requirements for the same plans set out in Part I, as previously described in this analysis.
In addition to these plans, the operator must also provide a description of the proposed navigational safety zones to protect project infrastructure against collision by vessels and aircraft, or a justification as to why navigational safety zones are not needed.
Ongoing requirements for operators
Part II of the Regulations also sets out the ongoing requirements that an operator must meet with respect to the conduct of work or activities, design requirements, protection against collision and navigational safety zones, and vessel considerations. These requirements under Part II are consistent with the requirements under the same headings in Part I, as previously described in this analysis.
PART III — Notification and investigation, reporting and record keeping
This Part applies to all types of ORE projects and requires the operator to notify the Regulator of any reportable incidents as soon as the circumstances permit and to investigate and provide to the Regulator, within 14 days, an incident report that describes detailed information related to the incident. A reportable incident is defined in the Regulations and includes any event that results in death, an injury that prevents an employee from working or performing their regular duties on any day after the injury, a fire, an explosion, a collision, any unauthorized or unexpected effect on the environment that is harmful, any damage to archaeological or cultural resources, a significant disruption to authorized work or activities due to unrelated activities or substance introduction, the impairment of a support craft or any equipment or system that is critical to safety, security or environmental protection, an impairment to the reliability of the power system, or the implementation of emergency response procedures.
The operator must also provide periodic summary reports to the Regulator every month during construction and decommissioning and abandonment work or activities of a wind energy project, and annually during the site assessment and operations work or activities of a wind energy project. Periodic summary reports must be submitted annually for all other types of ORE projects.
A final report summarizing the work or activity and a description of the state in which the operations site is being left must be provided to the Regulator within six months following the completion of the work or activity.
Finally, the Regulations require the operator to conserve at their principal place of business in Canada the documentation, information, and data resulting from the authorized activity, and to disclose that information to the Regulator, where requested.
Regulatory development
Consultation
The Regulations were subject to a comprehensive, multi-year engagement process that sought seek feedback from interested parties on the various stages of the regulatory development process. The Offshore Renewable Energy Regulations Initiative web page was developed to ensure stakeholders and the public were kept up to date on the initiative. Since the ORER Initiative was launched, more than 200 parties have been engaged.
Interested parties were invited by email to participate in the initiative’s engagement activities, including renewable energy industry companies/developers, industry associations, Indigenous groups and governments in coastal regions, certifying authorities, interested provinces and territories, regulators, other federal departments with ocean responsibilities, fishing groups, and environmental non-profit organizations.
Phase 1 of the engagement process took place between October 2020 and January 2021 and included an information webinar and a 90-day written comment period on a discussion paper (PDF) that outlined the proposed approach to regulating ORE activities in Canada. NRCan requested feedback on the guiding principles for the development of the Regulations, the various aspects to be addressed in the Regulations, the principal considerations to safety, security, and environmental protection throughout the life cycle of an ORE project, and the project timelines. The feedback received served to inform the next phase of the regulatory development process and was summarized in a summary paper (PDF) that was published on the ORE Initiative web page.
Phase 2 of the engagement process took place between December 2021 and February 2022, and again consisted of an information webinar and a 90-day written comment period on a technical requirements paper (PDF) that detailed the proposed requirements that would form the basis for the draft Regulations. In June 2022, NRCan followed up with a virtual workshop in response to technical questions that were received specific to the requirement for a certificate of fitness. The workshop provided a forum for discussion on the technical requirements related to the proposed role of a certifying authority and the general certification process for ORE facilities.
The input and advice received during these early engagements helped to inform the drafting of the Regulations. In May 2023, a draft version of the Regulations was shared with participants in the earlier phases of the regulatory development process and provided them with an opportunity to demonstrate how the feedback received in earlier engagements had been considered and incorporated into the draft Regulations. Feedback was received from 13 organizations, including two provincial governments (Nova Scotia and Newfoundland and Labrador), one Indigenous group, three offshore regulators (CER and the Offshore Petroleum Boards), two certifying authorities, four industry and/or industry associations, and one environmental non-governmental organization.
Notable feedback included suggestions to streamline the authorization process between life cycle phases of an ORE project and fine-tuning the technical requirements so that they would be more appropriate to the risks associated with ORE activities, which are inherently lower than the risks associated with offshore petroleum activities. In addition, feedback and questions were received related to how Indigenous coastal communities should be considered and communicated with; how results of an impact assessment required under the Impact Assessment Act would be factored into an ORE activity authorization; how impacts to other ocean users would be measured; and whether navigational safety zones would prohibit other ocean users from accessing the area where the ORE project is situated.
As a result of the feedback, the draft Regulations were revised to streamline the requirements related to the authorization process between life cycle phases, in particular, by combining the project construction and operations phases into one application for authorization, with two sets of conditions of authorization that must be met before the respective authorized activity (construction or operations) can commence. This approach was adopted in recognition that the application requirements for the construction and operations phases of a project would largely involve the same information; therefore, requiring that information be submitted in two separate applications would be duplicative. Further, the Regulator would need to know all relevant information about the intended operations and maintenance of a project in order to make a decision on whether to authorize the work related to the construction of the project.
In addition, as a result of the feedback, the requirements related to authorizations for repowering and/or life extension of a project were removed from the proposed Regulations. Given the ORE industry is still at the emerging stage globally and has yet to commence in offshore Canada, the prospect of repowering or needing to extend the life of a project is decades into the future, so the need to prescribe requirements related to that potential phase of a project at this point in the sector’s development is low.
In February 2024, the proposed Regulations, were pre-published in the Canada Gazette, Part I, and were subject to a 30-day public consultation period. Comments were received from two individuals and 11 organizations, comprising three environmental non-profit organizations, two Indigenous groups, two industry associations (renewable energy and shipping), two energy research organizations, one certifying authority and one energy services company. In addition, informal comments were received from contributing regulator partners.
The feedback received was largely supportive of the Regulations and, more broadly, the development of a comprehensive regulatory regime to support the transition to offshore renewable energy in Canada. The feedback included questions, input and suggested revisions to the regulatory text and format to improve the clarity regarding requirements, their applicability and other administrative provisions. Some comments were outside the scope of the Regulations, including feedback that focused on recommended amendments to the CER Act to align with the amendments to the Accord Acts proposed in Bill C-49. All comments received were reviewed in consultation with the CER, as the responsible regulator, with some resulting in modifications to the regulations.
Feedback received during the pre-publication period, along with any resulting changes to the Regulations, is summarized below.
Appropriateness of the Regulations for all types of ORE technologies and all phases of a wind energy project
An energy research organization raised concern that certain requirements, such as those related to the Certificate of Fitness and engagement of a Certifying Authority, may be less appropriate and overly onerous when using ORE technologies such as wave energy conversion for example, that are still in the demonstration stage of development. The organization suggested that the proposed Regulations, and the Regulatory Analysis, appeared to be focused mainly on offshore wind energy and that some of the requirements have the potential to create barriers to project development for ORE projects that use technologies that are deployed at a much smaller scale than offshore wind, and that are lower risk activities which are unlikely to involve significant impacts to safety, security and the environment.
The organization further noted their view that the small business lens analysis in the Regulatory Impact Analysis Statement that accompanied the proposed Regulations in the Canada Gazette, Part I, incorrectly assumed that ORE operators would not be small businesses and emphasized that it appeared that the Regulations were developed primarily with large-scale offshore wind projects in mind. They noted that many wave energy companies operating in Canada would have a staff complement of less than 100.
In addition, a renewable energy industry association commented that the requirements for a Management System, Safety Plan, Environmental Protection Plan and Emergency Response Plan may be overly robust for early activities that are lower risk and that there should be flexibility for some of those activities to not require an authorization.
The CER Act requires all work or activities related to an ORE project, regardless of the phase of the project, the scale and scope of the activity, or at what stage of development the proposed technology is in, to be authorized by the Commission, including any work or activities related to research and/or assessment conducted in relation to the exploitation or potential exploitation of an offshore renewable resource to produce energy. The Regulations cannot deviate from this legislated requirement; however, in consideration of the feedback, it was agreed that the Regulations should not unintentionally create a barrier to, or stifle innovation towards, new renewable energy technologies being used at a smaller, community-based level.
As a result, the Regulations have been modified to create two separate parts that will address the requirements for wind energy projects separately from the requirements of other types of ORE projects. Part 1 – Offshore Renewable Energy – Wind Energy – largely maintains the comprehensive regulatory requirements that were set out in the proposed Regulations that were pre-published in the Canada Gazette, Part I. Part 2 – Offshore Renewable Energy – other than Wind Energy – sets out a more streamlined regulatory framework that is founded on similar core planning requirements for wind energy for which an operator is obligated, those being, the requirement for a Safety Plan, Environmental Protection Plan and Emergency Response Plan; however, Part 2 does not impose requirements related to a Management System, Certifying Authority or Certificate of Fitness, which were considered to be overly onerous for the risk profile of smaller scale ORE projects that use technologies that are still in the demonstration stage of development. Part 3 addresses the regulatory requirements that apply to all types of ORE projects (under both Parts 1 and 2), and include requirements related to the notification and investigation of reportable incidents, record-keeping, and reporting requirements for operators.
The approach in Part 2 of the Regulations was adopted with the recognition that, should a proposed project be more complex in nature, the enabling legislation authorizes the Regulator to require any additional information in the application, and to impose any additional conditions of authorization with respect to approvals, that it considers necessary. This revised approach was positively received by the contributing commentor.
Part 1 continues to require a Management System, Safety Plan, Environmental Protection Plan and Emergency Response Plan for all phases of a wind energy project, given it is expected that the authorization will encompass the full suite of work and activities that an operator proposes to carry out during any given phase, and recognizing the inherent flexibility in the Regulations allowing the information submitted in support of an application and all documents and information submitted to the Regulator as a condition of an authorization to provide a level of detail that is proportionate to the scope, nature and complexity of the proposed work or activities.
It is expected that, over the course of the coming decade, ORE technologies will continue to evolve and those currently at the demonstration stage may move toward the commercial and large-scale development stage in the future, potentially increasing the complexity and risk potential of non-wind energy projects. Given this, and the certainty that there will inevitably be lessons learned once the Regulations are implemented and the industry starts to flourish with new projects under development, the Regulations will be added to NRCan’s Regulatory Stock Review Plan to be reviewed every five years, or sooner, to ensure the requirements continue to be comprehensive and appropriate in the face of continually changing ORE technologies and methodologies. These regular reviews will also provide an opportunity for requirements related to more specific types of ORE technologies to be added in the future, if needed.
Socio-economic assessments and assessments of the effects on rights, interests and concerns of Indigenous peoples
An Indigenous group and an environmental non-profit organization submitted comments on the requirement for the operator to submit, as part of its application for any authorization, an environmental and socio-economic assessment in respect of the proposed work or activities that addresses the factors referred to in paragraphs 298(3)(a) and (c)-(f) of the Actfootnote 1, which are the factors that the Commission must take into account in determining whether to issue an authorization.
Assessments of Indigenous rights, interests and concerns
The Indigenous group raised that the Regulations conflate the consideration of the factors referred to in paragraphs 298(3)(d) and (e), those being, “the interests and concerns of the Indigenous peoples of Canada, including with respect to their current use of lands and resources for traditional purposes” and “the effects on the rights of the Indigenous peoples of Canada recognized and affirmed by section 35 of the Constitution Act, 1982,” with the consideration of socio-economic factors, which is separately identified in the Act in paragraph 298(3)(c). They noted that the environmental and socio-economic assessment, as contemplated by the proposed Regulations, would be insufficient to properly assess “the interests and concerns of the Indigenous peoples of Canada, including with respect to their current use of lands and resources for traditional purposes”; or “the effects on the rights of the Indigenous peoples of Canada recognized and affirmed by section 35 of the Constitution Act, 1982,” and recommended that the assessment of the latter be separated out from the environmental and socio-economic assessment. To address this point, the Regulations have been revised to clearly distinguish between the requirement for an assessment that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the Act, and the environmental and socio-economic assessment, which would address the factors referred to paragraphs 298(3)(a), (c) and (f) of the Act.
In addition, the Indigenous group suggested that in carrying out the assessment that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the Act, the Regulations should require that the assessment must — at the election of the Indigenous group at issue — be co-designed and co-executed between the operator and the Indigenous group, with the operator providing reasonable funding to the Indigenous group for its participation in both the co-design and co-execution of the assessment. This recommendation goes beyond the scope of this regulatory proposal.
Both the CER Act and the Impact Assessment Act require processes to be established for the meaningful engagement of the public — and, in particular, the Indigenous peoples of Canada and Indigenous organizations, including the establishment of participant funding programs to facilitate participation in any impact assessment process or regional or strategic assessment processes under Impact Assessment Act, and any public hearings in respect of any matter the Commission considers it appropriate under the CER Act, including any steps leading to those hearings.
Environmental and socio-economic assessments
The environmental non-profit organization emphasized that the fundamental requirements of the environmental and socio-economic assessment process should be set out in law. They acknowledged, however, that the inherent complexity of these assessment processes makes guidance materials, like the CER’s Filing Manual which contains a substantial section on these environmental and socio-economic assessments, useful for communicating details that may otherwise be onerous to describe comprehensively in legislation.
This recommendation goes beyond the scope of this regulatory proposal; however, as the commentor noted, the CER has published extensive guidance in its Filing Manual on how proponents are to carryout environmental and socio-economic assessments, including an Early Engagement Guide that outlines the CER’s expectations for companies during the early engagement phase of a project that is not subject to an Impact Assessment. The CER has considerable experience using these guidance materials to ensure the operator’s assessment is appropriate for the nature and scale of the project, as well as the level of public interest in the project, and that it adequately addresses the predicted effects of the project. In addition, as previously noted, wind energy projects that are 10 turbines or more are designated projects under the Impact Assessment Act and will be subject to an Impact Assessment, and the requirement for an environmental and socio-economic assessment to be submitted as part of the application for authorization will be satisfied by that process. The Impact Assessment Agency of Canada (IAAC) provides extensive guidance and resources to help explain the federal government’s impact assessment process.
Offshore renewable energy in marine protected areas
Multiple parties provided feedback on their views that ORE exploration and exploitation should not be permitted to occur within any Marine Protected Areas (MPA) or areas of interest for future MPAs that are expected to count towards Canada’s marine conservation targets. It was further raised that Navigational Safety Zones should not drive marine traffic away from a project and into these protection and conservation areas. One environmental non-profit organization noted that some jurisdictions either prohibit or strictly limit offshore renewable energy installations in MPAs, outlining examples where offshore wind projects are prohibited within certain types of MPAs and where certain jurisdictions have used marine spatial planning to identify the specific zones in which offshore wind projects may be installed.
Siting for any future ORE development project, including the necessary licensing process for use of the seabed, will be subject to marine spatial planning exercises and significant public and Indigenous engagement, in advance of any application for authorization to conduct work or activities related to a proposed project being submitted. For example, in anticipation of future ORE activities off the coasts of Nova Scotia and Newfoundland and Labrador, two Regional Assessments (RA) have been launched under the Impact Assessment Act to provide information, knowledge, and analysis regarding future offshore wind development activities and their potential effects, to inform and improve future planning, licensing future project-specific federal impact assessments in these areas. Fisheries and Oceans Canada, Parks Canada and Environment and Climate Change Canada have each shared with the RA Committees the pertinent data related to marine protection and conservation objectives in these areas, with the DFO also sharing information related to its ongoing marine spatial planning work.
No revisions were made to the Regulations in response to this feedback; however, the matter will be considered during future land licensing processes.
Protection of wildlife
An individual requested that measures be taken to ensure that wildlife are not harmed while executing activities related to ORE projects. With respect to the Regulations, they raised that the operator’s plans should explicitly address wildlife protection, that projects should avoid wildlife migratory paths and use non-invasive ways to monitor wildlife, and that any injuries or deaths to animals should be reported to a wildlife rescue and rehabilitation organization.
The Act requires the operator to take all reasonable care to ensure the protection of the environment. The Regulations further obligate the operator to use the best available technologies for mitigating adverse effects on the environment that are economically feasible to implement, and to take all reasonable measures to prevent, or if prevention is not possible, to minimize the introduction into the environment anything that is likely to have an adverse impact on the environment. The operator must demonstrate in its application for authorization that the work or activities will be carried out in a manner that protects the environment and must submit an environmental assessment as part of the application. Environmental assessments are carried out to, among other things, evaluate the potential effects of the project on marine ecosystems, including marine life, seabirds, marine mammals and other organisms.
As a condition of any authorization, the operator must submit — for the Regulator’s approval — an Environmental Protection Plan that builds on, and incorporates findings from, the environmental assessment and sets out the procedures, practices and resources that will be put in place to protect the environment and manage environmental hazards, including any hazards that relate to wildlife. In addition to the requirements of these Regulations, the operator will also be subject to the requirements under other federal legislation pertaining to the environment and environmental protection, such as the Fisheries Act, Species at Risk Act and the Migratory Birds Convention Act, 1994 for various authorizations and/or permits. It is expected that the Environmental Protection Plan would address the requirements under other environmental legislation, including any mitigation measures and response procedures that are necessary to protect the environment.
The Regulations also require the operator to report to the Regulator any adverse impact on the environment, beyond those explicitly anticipated in the application for authorization, and to investigate that incident and submit a detailed investigation report to the Regulator within 14 days.
Given the foregoing, it was concluded that the Regulations appropriately address the measures operators must take to protect wildlife and the environment, more broadly, during the course of executing work and activities related to the ORE project.
Streamlining federal approvals
An energy research organization commented that there is limited mention in the Regulations of other federal and provincial agencies, noting their view that this represents a critical gap and a missed opportunity to align regulatory processes to make the approval of ORE projects in Canada more predictable, efficient, and holistic. The organization suggested that the Regulations should seek to streamline the processes and the agencies involved, or at least ensure data needs are transferable, rather than creating a more burdensome approval pathway that does not reflect or account for existing regulatory requirements. They further suggested that, at the very least, an integrated high-level overview or guidance document outlining all the permitting and licensing requirements at the federal and provincial levels would be helpful.
There are several authorizations, permits or approvals that will be required under other federal or provincial legislation. The CER has established numerous agreements with other federal and provincial regulators for the purpose of information sharing and streamlining approval processes. In addition, where a wind energy project is 10 turbines or more, an Impact Assessment will be required which will serve to further streamline the information sharing and approval process under the various applicable federal legislation given that the Commission must, pursuant to 299(b) of the CER Act, make its decision of whether to authorize the work or activity on the basis of the Impact Assessment reportfootnote 2. The Impact Assessment process is designed to support coordinated action among the various jurisdictions that have powers, duties and functions in relation to the assessment of the effects of designated projects.
It is also expected that the Regulator will, consistent with its existing practices, develop or expand existing guidelines and/or filing requirements to accompany these Regulations. These guidelines and/or filing requirements will help in clarifying the process and pathway towards authorization under the CER Act.
Ensuring consistency between these Regulations and future regulations under the amended Accord Acts
An environmental non-profit organization raised that once Bill C-49 receives Royal Assent and the amendments to the Accord Acts are in force, it will be important to ensure that the different legislative frameworks governing ORE in the country is consistent.
These Regulations will form the basis of the future proposed Regulations under the amended Accord Acts, which are expected to be pre-published in the Canada Gazette, Part I, for public comment in early 2025. The intention is for the three sets of ORE regulations to be nearly identical between the three administrative areas, which will promote consistency in application/implementation and reduce any potential confusion for investors to understand the “Canadian regime.”
Certifying authority and certificate of fitness
A certifying authority commented that the Regulations should require that an independent assessment of the decommissioning and abandonment plan be carried out by the approved certifying authority to conduct, given the certificate of fitness is required to be maintained valid for as long as the facilities remain in operation.
Mandatory involvement of a third-party verification agent at the decommissioning and abandonment phase of a project is inconsistent with the regulatory approach taken by other jurisdictions globally. Although the operator may engage a certifying authority or other independent third party at the decommissioning and abandonment phase, making this a regulatory requirement would result in Canada being more costly and less competitive that other jurisdictions by comparison. The review and approval of the decommissioning and abandonment plan, as well as any technical oversight of the execution of decommissioning and abandonment activities required, would be undertaken by the qualified technical staff of the Regulator.
The same organization also suggested that the Regulations should require that the certifying authority is notified of any reportable incidents to allow them to determine the incident’s impact on the Certificate of Fitness; however, many of the types of incidents that must be reported to the Regulator and investigated do not relate to the facilities. As a result, no changes were made to the Regulations. If there are incidents that relate to the facilities, the Certifying Authority would become informed through the operator’s and regulator’s review of the incident.
An environmental non-profit organization suggested that rather than requiring the involvement of a certifying authority for the purpose of third-party verification, that government experts should be employed to review projects to ensure full independence, as they caution the potential for issues with professional competence, bias and conflicts of interest that may arise from a professional reliance regime. They further suggested that, in the absence of this, the Regulations should specify that this approach be subject to review within five years of coming into force.
The role of a certifying authority has been successfully used in Canada’s offshore petroleum regime for nearly 30 years and the reliance on a third-party verification agent at the construction phase of a wind project is used in other jurisdictions globally. The Regulations contain requirements that address any potential conflict of interest, and given the certifying authority reports directly to the Regulator under the Regulations, the possibility of bias is minimized. Notwithstanding, as previously noted, these Regulations will be added to NRCan’s Regulatory Stock Review Plan and will be reviewed every five years, or sooner, to ensure the requirements continue to be comprehensive and appropriate for this new industry.
Technical requirements
Various technical comments were received which resulted in changes to the Regulations.
A certifying authority commented that the Facilities Design Report should include a list of the industry standards and best practices that were used in the design of the facilities, equipment and systems, as well as any data sets that were used in establishing operational and extreme loading conditions, and that it include a description and associated drawings of the project’s major mechanical components. An individual also suggested that the report should include both structural integrity information and, for any floating infrastructure, information on the stability and motion response characteristics. These suggested additions were incorporated into the section on Facilities Design Report.
A renewable energy industry association questioned the appropriateness of the requirement to have a support craft within a 20-minute response time of a facility for ORE activities. The association suggested that the requirement originated from, and is more appropriate for, offshore petroleum drilling and production operations, which are regularly attended installations with a large number of personnel on board. The Regulations were updated to align with requirements that were published in February 2024 for the offshore petroleum regimefootnote 3 and relate to rescue boat availability for vessel-based programs, which is more akin to the type of work involved in ORE projects. With this revision, rescue boats would always be required when there are personnel in the offshore area and the requirement that every vessel used in the authorized work or activities be equipped with a rescue boat was no longer needed as it was redundant, which addressed another comment from the renewable energy industry association that such a requirement was not reasonable for all vessels.
The renewable energy industry association also questioned why the Regulations require fuel storage tanks on any facilities equipped with aircraft landing areas, noting that fuel storage tanks are not a mandatory requirement under the offshore petroleum regime. The regulatory requirements for landing areas have been aligned with the recently published Regulations for the offshore petroleum regime. For clarity, under these Regulations, fuel storage tanks are only required on facilities when those facilities are also equipped with helicopter landing areas.
Navigational safety zones
A shipping industry association conveyed its appreciation that marine transportation and vessel traffic had been taken into consideration in the Regulations and suggested that the section on navigational safety zones be amended to require notification to Transport Canada, in addition to the Canadian Coast Guard and the Canadian Hydrographic Services, of location of facilities, the boundaries of any navigational safety zones, and any risks to navigation. They noted that doing so would ensure alignment across key government agencies and promote timely communication of proposed navigational changes that could affect the shipping industry. The Regulations were amended to include this suggestion.
A renewable energy industry association commented that the requirement for the operator to ensure vessels approaching a navigational safety zone are notified of the safety zone’s boundaries and any hazards related to the facilities within that safety zone, may not be possible for normally unattended facilities. In review, it was determined that the intent of this provision is already achieved by the requirement for the operator to notify the Canadian Coast Guard and the Canadian Hydrographic Services, of location of facilities, the boundaries of any navigational safety zones, and any risks to navigation. These organizations will, in turn, update the Notice to Mariners and nautical charts accordingly, and vessel operators will have access to the necessary information through those notices and charts. Therefore, the requirement was considered redundant and was subsequently deleted.
Equivalencies
Feedback from the renewable energy industry association and an energy research organization raised the need for the Regulations to be flexible enough to allow for the adoption of innovative and new technologies, with the former noting that there should be specific authority for the regulator to accept equivalencies in areas where technology and best practices change.
The Regulations are a combined approach of both performance-based and management-based regulations, which provide the flexibility necessary to support the use of innovations in science, technologies, and methodologies that would increase safety, security, and environmental protection. Furthermore, the addition of the new Part 2 addressing ORE projects, other than wind energy projects, provides an approach for projects that use these newer technologies that may be still in the demonstration stage. This approach will ensure the Regulations have the necessary flexibility to be “right sized” and better matches the regulatory requirements to the risk profile of the expected ORE projects, recognizing the Commission’s authority to impose any additional conditions of authorization with respect to approvals that it considers necessary.
The Act also authorizes the Commission to make orders exempting operators from any or all of the provisions of these Regulations in order to, among other things, ensure the safety and security of persons, the safety and security of facilities or abandoned facilities, and the protection of property and the environment.
Reporting requirements
A regulator partner raised that the requirement for a final report to be submitted within three months following the completion of all authorized work and activities may not be sufficient time for an operator to provide the Regulator with a detailed, comprehensive report and suggested that up to six months may be more appropriate and to avoid rushed reports. The Regulations were revised to allow the operator up to six months to submit its final report.
Forecasted future project activity
An energy research organization suggested that the assumptions made in the Regulatory Analysis on the number of projects expected in the next twenty years is overly conservative. They commented that it is a pessimistic outlook that does not align with expected ORE advances, global projections, or Canada’s legislated climate and electrification policies.
The assumptions made in the regulatory analysis are based on information in the public domain, from both industry and provincial governments, on stated goals and objectives related to a future offshore wind sector. The Regulatory Analysis has been updated to include publicly available information on potential future non-wind ORE applications in coastal British Columbia.
Transparency
An environmental non-profit organization commented that there are several pieces of information and documents required of operators that the Regulations do not require to be disclosed to the public, noting their view that the lack of transparency may serve to impede the goals of the ORE regulatory regime of safety, security, and environmental protection. The organization acknowledged that the CER Act requires decisions, orders, and recommendations to be made publicly available and that the CER’s practice is to make information available related to public hearings/reviews, inspection officer reports and notice of violations. They further acknowledged that some information should not be made publicly available, as it could compromise safe operations and/or security at the facilities.
The CER has multiple online regulatory databases that contain extensive information related to projects at all stages, from initial application and hearings information and correspondence to ongoing activities and transactions conducted at the CER, to compliance and enforcement correspondence. In addition, the CER also makes biophysical, socio-economic, and regional data and information on projects available online. As the commentor pointed out, some safety and security sensitive information should not be made publicly available; however, beyond that type of information, it is the CER’s practice to make all other information publicly available.
Modern treaty obligations and Indigenous engagement and consultation
In accordance with the Cabinet Directive on the Federal Approach to Modern Treaty Implementation, an analysis was undertaken to determine whether these Regulations are likely to give rise to modern treaty obligations. The assessment examined the geographic scope and subject matter of these Regulations in relation to modern treaties in effect and concluded that implementation of these Regulations is unlikely to impact the rights, interests, or self-government provisions of treaty partners.
All people in Canada would benefit from ensuring that ORE projects are carried out in a manner that ensures environmental protection and the safety and security of persons and property. The CER Act requires the Commission to consider, in determining whether to issue an authorization, any Indigenous knowledge that has been provided to the Commission, as well as the interests and concerns of the Indigenous peoples of Canada, including with respect to their current use of lands and resources for traditional purposes, and any effects on the rights of the Indigenous peoples of Canada recognized and affirmed by section 35 of the Constitution Act, 1982.
Instrument choice
Regulations are needed to operationalize Part 5 of the CER Act. The Regulations would ensure that consistent rules, with compliance and enforcement mechanisms, related to safety, security, and environmental protection are applied to all ORE projects and would provide the necessary clarity and certainty for the nascent ORE industry to develop in Canada. No non-regulatory options were considered.
Regulatory analysis
Benefits and costs
The Regulations establish the framework for ORE projects to be carried out in a manner that protects safety, security, and the environment, which could contribute to federal and provincial renewable energy targets. The benefits arising from this industry cannot be solely attributed to the Regulations, but rather, are associated with the complete legislative regime for ORE under the CER Act.
Future operators of all types of ORE projects would assume incremental costs associated with the Regulations, as compared to what may be carried under the baseline scenario (no regulations), including labour costs related to the time spent on respecting mandatory reporting and inspection requirements. Operators of wind energy projects would also incur labour costs related to the involvement of a certifying authority during the operations phase of the project. The incremental costs are expected to average less than $1 million yearly. The benefits and costs are considered qualitatively in this analysis.
Analytical framework
Under the Policy on Cost-Benefit Analysis, a cost-benefit analysis must consider the incremental impacts of the Regulations, as measured by the difference between the baseline scenario and the scenario in which the Regulations are implemented, over the same period. The baseline scenario considers what is likely to happen in the future if the Government of Canada did not implement the Regulations, and it considers the changes that are likely to happen under normal circumstances without the Regulations in place. Any incremental benefits and costs related to the introduction of the Regulations (the “regulatory scenario”) are then assessed by comparing them against the baseline scenario.
In this analysis, the baseline scenario is one in which the legislative framework exists under Part 5 of the CER Act, which gives the Commission the authority to authorize work and activities related to ORE projects and powerlines, and to establish conditions on those authorizations that must be satisfied by an operator. It is expected that in the baseline scenario, the Regulator would exercise its authority under the Act to establish minimum requirements through conditions of authorization related to safety, security, and environmental protection at all stages of the development of an ORE project — regardless of the type of ORE project (wind energy or non-wind energy). In addition, based on feedback from renewable energy industry companies/developers and industry associations during early engagement, as well as feedback from regulators in other jurisdictions, it is expected that in the baseline scenario, operators will follow industry standards and best practices in the development of a project. For example, operators of wind energy projects typically utilize the services of a third-party certification company for insurance purposes, to verify that the project facilities have been fabricated, constructed, and installed in a manner that ensures the safety, integrity, and reliability of the project.
The Regulations do not prescribe any specific technology or methodology that must be used by an operator of a project; rather, they establish requirements related to the planning, management, and execution of proposed work or activities that an operator must satisfy prior to commencing any authorized work. It is expected that an operator, particularly those proposing larger projects that would use more complex technologies, would voluntarily establish many of these plans and programs, as they would be consistent with best management practices for companies working in the offshore renewable energy industry. Notwithstanding, it is expected that for all types of ORE projects, the Commission would require, through conditions on those authorizations, that an operator implement these appropriately scoped planning requirements, such as the Safety Plan, Environmental Protection Plan and Emergency Response Plan, even for smaller-scale projects that propose to use less complex technologies.
In response to a concern raised by a stakeholder during the CGI comment period that some of the requirements set out in the proposed Regulations were less appropriate and overly onerous for ORE projects that propose to use less complex technologies that are deployed at a much smaller scale than offshore wind, the Regulations were revised and modified to create two separate parts that will address the requirements for wind energy projects (Part 1) separately from the requirements of other types of ORE projects (Part 2). Requirements set out in Part 2 are similar to in Part 1, but adjusted to reflect the fact that these types of ORE projects are expected to be smaller in scale and less complex in nature. Part 2 does not require a Management System, Certifying Authority or Certificate of Fitness, which were considered to be overly onerous for the risk profile of smaller scale ORE projects that use technologies that are still in the demonstration stage of development. For ORE projects, in particular, more complex projects such as those using wind energy, the duration of each phase of the life cycle (site assessment, construction and operations, decommissioning and abandonment) and the interval between each phase will vary depending on the project, operator, and the time required to obtain all the necessary authorizations under the Regulations and any other applicable federal legislation. The potential impacts of the Regulations will not be immediately discernable; therefore, the analysis considers a 20-year time frame to identify any incremental impacts that may arise from the Regulations.
Based on the interest expressed by the offshore wind development industry in the early engagement stages, it is anticipated that the majority of wind energy projects will be carried out in the Canada–Nova Scotia and Canada–Newfoundland and Labrador offshore areas. The Canada–Nova Scotia offshore area will likely see the earliest activity, a conclusion drawn following the Government of Nova Scotia’s announcement of its Offshore Wind Roadmap (PDF) and intent to offer leases for five gigawatts of offshore wind energy by 2030. This move could lead to the development of four commercial-scale wind projects within the analysis period. Although the Government of Newfoundland and Labrador has focused its early wind energy efforts on onshore land leases in support of a wind-to-hydrogen industry, it is expected that there would be at least two commercial-scale projects in the Canada–Newfoundland and Labrador offshore area during the period of analysis, given the prevailing wind speeds off the coast of that province and its potential for wind development. Finally, it is expected that British Columbia may have one smaller-scale wind energy project, and one or more smaller scale non-wind energy projects during the period of analysis. Each project would have one operator, resulting in an expected seven operators or affected businesses in the next 20 years.
Benefits of the Regulations
Benefits to governments and the public
The Regulations will provide transparency and certainty for Canadians, the industry, and other stakeholders with respect to the requirements and obligations to operate and maintain an ORE project. The Regulations combine elements of outcome-based and management-based regulatory design to promote the continual advancement of safety, security, and environmental protection outcomes, while providing the necessary flexibility for the Regulations to evolve over time with the continual change in best available technologies and methodologies.
Benefits for industry
The Regulations require operators of all types of ORE projects to identify, manage, and mitigate risks to safety, security and the environment. Operators are obligated to follow safety, security, reliability, and environmental protection standards and, in the case of wind energy projects, seek third-party verification to confirm that the wind energy project facilities are constructed and installed correctly and are fit for purpose. Operators of wind energy projects are also required to maintain these standards throughout the duration of operations. The Regulations clarify the application and authorization process to allow all types of ORE projects to move forward, paving the way for the successful development of new ORE projects and the emergence of a new industry.
Costs of the Regulations
Compliance costs to industry
In the baseline scenario, it is expected that operators of all types of ORE projects will conform with industry standards, adopt best practices and, in the case of operators of wind energy projects, will employ the services of a third-party certification company without being required to do so by regulations. Costs associated with these activities are not considered incremental to these Regulations.
Since the CER Act authorizes the Regulator to establish minimum requirements through conditions of authorization related to safety, security, and environmental protection, costs attributable to the Regulations stem only from the mandatory reporting and inspection requirements for all types of ORE projects. As noted in the “Description” section, these requirements include notifying the Regulator of reportable incidents, investigating the incidents, and providing the final investigation report to the Regulator. They also include the provision of periodic summary reports to the Regulator. This cost would take the form of wages paid to personnel for the hours of work associated with the mandatory reporting and inspections. For example, under the scenario outlined above, it is estimated that there would be an average of eight incidents reported each year once all projects are operational, with each report requiring 40 hours to complete.
The operators of wind energy projects would also bear incremental costs with respect to the certifying authority’s involvement in the project’s operations life cycle phase. In the baseline scenario, it is assumed that the operator would engage the services of a certifying authority during construction of the wind energy project to satisfy insurance requirements; however, it is unlikely that the operator would continue to utilize the services of the certifying authority during regular operations without a regulatory requirement to do so. Therefore, the costs associated with the certifying authority in the operations phase of a wind energy project, which include those associated with periodic monitoring and inspection of facilities, equipment and systems to verify their continued integrity, are incremental costs and would also take the form of wages paid to personnel for the hours of work associated with the mandatory inspections and reporting by the certifying authority, which would be billed back to the operator.
These costs would be carried as projects develop and advance in their life cycle. Total costs would depend on the number and size of projects under development during the analysis period.
Small business lens
An analysis under the small business lens concluded that the Regulations would affect a minimal number of Canadian small businesses should they apply to become operators of smaller scale, non-wind ORE projects, while wind energy operators are not expected to meet the definition of “small business.”
The Regulations have been revised from those proposed in the Canada Gazette, Part I, to address the concern that some elements contemplated in those proposed Regulations, such as Management System, Certifying Authority and Certificate of Fitness, would be overly onerous and costly for the risk profile of projects that utilize smaller scale ORE technologies, such as wave energy conversion, that are still in the demonstration stage of development and which may be operated by small businesses. The Regulations now provide an approach for those projects utilizing non-wind technologies that is reflective of the fact that these types of projects are expected to be smaller in scale and less complex in nature. The revisions, which no longer require a Management System, Certifying Authority and Certificate of Fitness for non-wind projects, are expected to help in reducing any potential or perceived barrier to, or stifle innovation towards, new renewable energy technologies from being used at a smaller, community-based level.
The Regulations also implement a blend of management-based and outcome-based requirements and do not impose prescriptive technical requirements that must be adopted. This blended approach provides the necessary flexibility to allow for innovation and cost reductions for all types of ORE projects, without diminishing safety and environmental protection.
One-for-one rule
The one-for-one rule applies, since there is an incremental increase in the administrative burden on business, and the Regulations are considered burden in under the rule. The Regulations impose administrative costs that arise from the requirements to conserve records that are submitted to the Regulator in support of the application or authorization, the results of surveys conducted, and documents that demonstrate that the work or activities were carried out in the manner proposed by the operator and in compliance with the Regulations.
Given this is an industry with no existing activities in Canada and that it takes time for an operator to obtain all necessary land licences and authorizations under the Regulations and any other applicable federal legislation, it is expected that the administrative burden associated with the Regulations will not be incurred until two years after the Regulations enter into force and that they will be limited to those records arising within the first decade following the Regulations coming into force, related to the site assessment and construction phases of two wind projects, and the site assessment and deployment activities related to one wave energy conversion project.
The individual responsible for conserving records will likely vary, depending on the nature of the record. However, the 2022 average hourly wage for the National Occupational Classification (NOC) of professional occupations in natural and applied sciences of $46.63 is used as a proxy to estimate the hourly cost. It is estimated that the average time required to conserve a record to be 5 (five) minutes.
The Regulations result in an additional annualized cost of $1,281 (2012 Can$footnote 4) of administrative burden as estimated using the Red Tape Reduction Regulations’ prescribed method. A new regulatory title (title in) is introduced.
Regulatory cooperation and alignment
The Regulations are not related to an international agreement or obligation, nor do they have any impacts related to a work plan or commitment under a formal regulatory cooperation forum.
The Regulations were, however, inspired in part by the regulatory framework in the United States for the operational safety and environmental protection of ORE projects in U.S. coastal waters. In addition, select elements of Canada’s existing regime for offshore petroleum activities were also adopted, where appropriate, to allow for consistency between the offshore regimes while ensuring that the requirements for ORE were not unnecessarily burdensome, given the risk profile for ORE is much lower than that of petroleum.
It is NRCan’s intent to replicate, to the extent possible, the Regulations in the Canada–Nova Scotia and Canada–Newfoundland and Labrador offshore areas. The governments of Nova Scotia and Newfoundland and Labrador have been consulted throughout the regulatory development process and have provided input into the Regulations.
Effects on the environment
In accordance with the Cabinet Directive on the Environmental Assessment of Policy, Plan and Program Proposals, a preliminary scan was conducted for the Regulations and concluded that a strategic environmental assessment is not required.
Gender-based analysis plus
A gender-based analysis plus (GBA+) assessment was conducted as part of the development of the Regulations and no GBA+ impacts have been identified. The Regulations establish requirements that operators must meet in carrying out work and activities related to ORE projects to ensure environmental protection and the safety and security of persons and property. The Regulations are not expected to result in differential impacts on GBA+ categories of stakeholders as the ORE sector develops, nor to the public at large.
Implementation
The Regulations come into force on the day they are registered. It is anticipated that the CER may develop guidance materials to assist interested parties and future operators in the interpretation of these Regulations, where the CER has determined that additional guidance could be helpful. Consistent with its regular practice, the CER will update its website to provide information about these Regulations and would work to address any questions that interested parties and future operators have with respect to the interpretation and compliance of the Regulations.
Compliance and enforcement
Compliance and enforcement activities will follow established CER approaches and procedures to monitor compliance under, and enforce, the CER Act and the regulations made thereunder. Part 2 of the Act sets out the powers of inspection officers to administer and enforce the Act and the Regulations, for the purpose of ensuring the safety and security of persons and facilities, as well as the protection of property and the environment.
The Regulator may become aware of non-compliance through regular inspections, condition reviews, meetings, audits, and incidents and near misses to be reported to the CER under the Regulations through immediate or periodic reporting requirements. The CER has a variety of compliance and enforcement tools, such as notices of non-compliance, inspection officer orders, warning letters, Commission orders or letters of direction, suspension of operations, administrative monetary penalties and prosecution. More than a single tool may be employed to obtain or promote compliance, deter future non-compliance or to prevent harm.
An inspection officer who has reasonable grounds to believe that a requirement of the CER Act or its regulations is being, or has been, contravened may order a person to stop the contravention. They may also order a person to stop doing something that may cause a hazard to the safety or security of persons or cause damage to property or the environment, and to take any measure that is necessary to prevent or mitigate those hazards, or to ensure compliance and/or mitigate the effects of non-compliance with the Act and its regulations.
Failure to comply with an order from the Commission or an inspection officer is a prosecutable offence under the Act, and penalties include, on summary conviction, a fine up to $100,000, imprisonment for a maximum term of one year, or both; and, on conviction of an indictment, a fine up to $1 million, or imprisonment for a maximum term of five years, or both. The CER Act also provides the CER with the authority necessary to establish, with the approval of the Governor in Council, regulations related to the designation of violations that are subject to administrative monetary penalties, as well as the determination of the amount payable as the penalty.
Contact
Kim Phillips
Senior Regulatory Officer
Renewable and Electrical Energy Division
Department of Natural Resources
Telephone: 902‑402‑0285
Email: nrcan.offshorerenewables-renouvelablesextracotieres.rncan@canada.ca